14039 W PIERCE ST 91331
Certificate Information: 14039 W PIERCE ST 91331
- Application / Permit
- 25010-20000-02192
- Plan Check / Job No.
- B25VN14165
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY DETACHED ACCESSORY DWELLING UNIT (ADU 2 -NORTH) TO COMPLY WITH GCS 66323(a)(4) PER ENGINEERING. NFPA-13D FIRE SPRINKER THRU-OUT
- Permit Issued
- Issued on 7/29/2025
- Issuing Office
- Current Status
- CofO in Progress on 4/27/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2025 | ALFRED RAMIREZ |
| Corrections Issued | 6/10/2025 | ALFRED RAMIREZ |
| Quality Review Completed | 6/13/2025 | STEVEN KIM |
| Building Plans Picked Up | 6/13/2025 | APPLICANT |
| Applicant returned to address corrections | 7/15/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 7/29/2025 | ALFRED RAMIREZ |
| Issued | 7/29/2025 | APPLICANT |
| CofO in Progress | 4/27/2026 | MISAEL ESPARZA |
Permit Application Clearance Information
| Construction within easement | Cleared | 6/13/2025 | WALTER RAMIREZ |
| Address approval | Cleared | 6/16/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 6/23/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 6/25/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/4/2025 | Partial Approval | MICHEL ABAJAN |
| Pre-Inspection | 8/4/2025 | Partial Inspection | MICHEL ABAJAN |
| METHANE-Subgrade | 8/6/2025 | Approved | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 8/11/2025 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 8/11/2025 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 8/11/2025 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 8/11/2025 | Approved | MICHEL ABAJAN |
| Deputy Wood Construction | 10/9/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 10/27/2025 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 10/27/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/27/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/3/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 12/3/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/3/2025 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 12/3/2025 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 12/3/2025 | Approved | MICHEL ABAJAN |
| Insulation | 12/12/2025 | Corrections Issued | LOUIS ESCOTO |
| Interior/Exterior Lathing | 12/12/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 12/12/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 12/23/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 3/16/2026 | Approved | MICHEL ABAJAN |
| Final | 3/16/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| Gas Test | 3/16/2026 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 3/16/2026 | Approved | MICHEL ABAJAN |
| HVAC-Final | 3/16/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 3/16/2026 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 3/16/2026 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 3/16/2026 | Corrections Issued | MICHEL ABAJAN |
| Smoke Detectors | 3/16/2026 | Approved | MICHEL ABAJAN |
| Final | 4/7/2026 | Corrections Issued | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 4/7/2026 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 4/7/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 4/23/2026 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 4/23/2026 | Approved | MISAEL ESPARZA |