8641 N COLLETT AVE 91343
Certificate Information: 8641 N COLLETT AVE 91343
- Application / Permit
- 25010-20000-02126
- Plan Check / Job No.
- B25VN13763
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached accessory dwelling unit per GC 66323(a)(2)
- Permit Issued
- Issued on 6/29/2025
- Issuing Office
- Current Status
- CofO Issued on 2/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2025 | SHANGQIN XIE |
| Corrections Issued | 5/24/2025 | SHANGQIN XIE |
| Applicant returned to address corrections | 6/5/2025 | SHANGQIN XIE |
| Plan Check Approved | 6/9/2025 | SHANGQIN XIE |
| Issued | 6/29/2025 | APPLICANT |
| CofO in Progress | 2/5/2026 | GAREN HAYRAPETYAN |
| Permit Finaled | 2/12/2026 | RUBEN SALAS |
| CofO Issued | 2/12/2026 | RUBEN SALAS |
| Permit Finaled | 2/12/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Tract Map conditions | Cleared | 5/28/2025 | JASON CHAN |
| Address approval | Cleared | 5/30/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 6/4/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 6/6/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Homescapes Design And Construction Inc; Lic. No.: 1055222-B | 16133 VENTURA BLVD SUITE 700 ENCINO, CA 91436 |
| Engineer | Santos,, Michael; Lic. No.: C77657 | 16202 ORION AVE CHINO, CA 91708 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/27/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/29/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 9/3/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2025 | Partial Approval | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 9/24/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 9/24/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 9/24/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 9/24/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 9/24/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 10/24/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 10/24/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 10/24/2025 | Partial Approval | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 10/24/2025 | Approved | GAREN HAYRAPETYAN |
| Sewer | 10/24/2025 | Approved | GAREN HAYRAPETYAN |
| Underground Mechanical | 10/24/2025 | Approved | GAREN HAYRAPETYAN |
| Wood Frame | 10/24/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 10/29/2025 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 10/31/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 11/20/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 11/20/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 1/30/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 1/30/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 1/30/2026 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 1/30/2026 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 1/30/2026 | SGSOV No Gas | GAREN HAYRAPETYAN |
| Service/Power Release | 1/30/2026 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 1/30/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 2/5/2026 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Service/Power Release | 2/5/2026 | Approved | GAREN HAYRAPETYAN |