17239 W SUNBURST ST 91325

Certificate Information: 17239 W SUNBURST ST 91325

Application / Permit
25010-20000-02099
Plan Check / Job No.
B25VN13501
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU (682 SF) WITH PATIO COVER AND OUTDOOR BBQ GRILL AREA (778 SF)
Permit Issued
Issued on 8/29/2025
Issuing Office
Current Status
CofO in Progress on 5/27/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/16/2025 APPLICANT
Assigned to Plan Check Engineer 6/20/2025 JOHN MESIAS
Corrections Issued 6/20/2025 JOHN MESIAS
Applicant returned to address corrections 8/14/2025 JOHN MESIAS
Plan Check Approved 8/29/2025 JOHN MESIAS
Issued 8/29/2025 APPLICANT
CofO in Progress 5/27/2026 CHRISTOPHER ROJAS

Permit Application Clearance Information

Construction near power lines Cleared 7/28/2025 ENRIQUE ACOSTA
Address approval Cleared 8/1/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 8/1/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 8/1/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/4/2025 LEE GUILBEAUX
Sewer availability Cleared 8/4/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/5/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Pre-Inspection 9/5/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 9/11/2025 Partial Approval NICHOLAS TROWBRIDGE
Excavation/Setback/Form/Re-Bar 9/23/2025 Corrections Issued NICHOLAS TROWBRIDGE
Underground Mechanical 10/3/2025 Corrections Issued NICHOLAS TROWBRIDGE
Deputy Drilled-In Anchors 10/6/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 10/30/2025 Approved NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 12/3/2025 Partial Approval JUAN VALENZUELA
Sewer 12/3/2025 Approved JUAN VALENZUELA
Underground Mechanical 12/3/2025 Partial Approval JUAN VALENZUELA
Deputy Wood Construction 12/8/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/9/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 12/9/2025 Approved JENNIFER RABUCHIN
Shower Pan 12/15/2025 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 1/7/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 1/7/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 1/7/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 2/9/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 2/9/2026 Approved CHRISTOPHER ROJAS
HVAC-Rough 2/9/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 2/9/2026 Partial Approval CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 2/9/2026 Approved CHRISTOPHER ROJAS
Insulation 2/13/2026 Approved MICHAEL CORTEZ
Drywall Nailing 2/25/2026 Approved MICHAEL CORTEZ
Gas Test 3/31/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 5/18/2026 Approved KEVIN BERBERYAN
Final 5/18/2026 Corrections Issued KEVIN BERBERYAN
Green Building Final 5/18/2026 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Final 5/18/2026 Approved KEVIN BERBERYAN
PLUMBING-Final 5/18/2026 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 5/18/2026 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 5/18/2026 Approved KEVIN BERBERYAN
Final 5/26/2026 Partial Inspection KEVIN BERBERYAN
Final 5/27/2026 OK to Issue CofO CHRISTOPHER ROJAS