17239 W SUNBURST ST 91325
Certificate Information: 17239 W SUNBURST ST 91325
- Application / Permit
- 25010-20000-02099
- Plan Check / Job No.
- B25VN13501
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU (682 SF) WITH PATIO COVER AND OUTDOOR BBQ GRILL AREA (778 SF)
- Permit Issued
- Issued on 8/29/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/27/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2025 | JOHN MESIAS |
| Corrections Issued | 6/20/2025 | JOHN MESIAS |
| Applicant returned to address corrections | 8/14/2025 | JOHN MESIAS |
| Plan Check Approved | 8/29/2025 | JOHN MESIAS |
| Issued | 8/29/2025 | APPLICANT |
| CofO in Progress | 5/27/2026 | CHRISTOPHER ROJAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/28/2025 | ENRIQUE ACOSTA |
| Address approval | Cleared | 8/1/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 8/1/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 8/1/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/4/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/5/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Pre-Inspection | 9/5/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 9/11/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Excavation/Setback/Form/Re-Bar | 9/23/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 10/3/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Deputy Drilled-In Anchors | 10/6/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 10/30/2025 | Approved | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2025 | Partial Approval | JUAN VALENZUELA |
| Sewer | 12/3/2025 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 12/3/2025 | Partial Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 12/8/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/9/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 12/15/2025 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 1/7/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 1/7/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 1/7/2026 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 2/9/2026 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 2/9/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 2/9/2026 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 2/9/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 2/9/2026 | Approved | CHRISTOPHER ROJAS |
| Insulation | 2/13/2026 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 2/25/2026 | Approved | MICHAEL CORTEZ |
| Gas Test | 3/31/2026 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 5/18/2026 | Approved | KEVIN BERBERYAN |
| Final | 5/18/2026 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 5/18/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Final | 5/18/2026 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 5/18/2026 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 5/18/2026 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 5/18/2026 | Approved | KEVIN BERBERYAN |
| Final | 5/26/2026 | Partial Inspection | KEVIN BERBERYAN |
| Final | 5/27/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |