13129 W HOYT ST 91331

Certificate Information: 13129 W HOYT ST 91331

Application / Permit
25010-20000-02098
Plan Check / Job No.
B25VN13493
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRREGULAR SHAPED 33'-0" X 19'-6" DWELLING PER SB9 - PER ENGINEER *NFPA-13D FIRE SPRINKLERED THROUGHOUT
Permit Issued
Issued on 8/22/2025
Issuing Office
Current Status
CofO in Progress on 7/14/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/13/2025 APPLICANT
Assigned to Plan Check Engineer 5/15/2025 SELLA BENYAMIN
Assigned to Zoning Architect 5/15/2025 BENNY WONG
Corrections Issued 5/21/2025 DANIEL ABRAMYAN
Quality Review Completed 5/22/2025 OMID HEDAYAT
Applicant returned to address corrections 7/11/2025 DANIEL ABRAMYAN
Plan Check Approved 8/21/2025 SELLA BENYAMIN
Issued 8/22/2025 APPLICANT
CofO in Progress 7/14/2026 MICHEL ABAJAN

Permit Application Clearance Information

ZI Cleared 5/30/2025 DALIA MOKAYED
ZI Cleared 5/30/2025 DALIA MOKAYED
Hydrant and Access approval Cleared 6/4/2025 GILBERT URREA
Address approval Cleared 6/6/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/6/2025 LEE GUILBEAUX
Permit Cleared 6/6/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 6/6/2025 LEE GUILBEAUX
Sewer availability Cleared 6/6/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/6/2025 LEE GUILBEAUX
Senate Bill 9 Cleared 6/11/2025 DALIA MOKAYED
Zoning Plan Check Cleared 6/12/2025 BENNY WONG

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/12/2025 Approved MICHEL ABAJAN
METHANE-Barrier 9/12/2025 Approved MICHEL ABAJAN
METHANE-Subgrade 9/12/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 9/22/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 9/22/2025 Partial Approval JENNIFER RABUCHIN
Insulation 9/23/2025 Partial Approval NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 9/25/2025 Corrections Issued KEVIN BERBERYAN
Deputy Wood Construction 10/1/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 10/1/2025 Partial Approval KEVIN BERBERYAN
Deputy Wood Construction 11/12/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 11/18/2025 Approved MICHEL ABAJAN
Green Building Rough 11/18/2025 Approved MICHEL ABAJAN
METHANE-Rough 11/18/2025 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 11/18/2025 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 11/18/2025 Approved MICHEL ABAJAN
Underground Mechanical 11/26/2025 Approved MICHEL ABAJAN
Insulation 12/1/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 12/1/2025 Approved MICHEL ABAJAN
Drywall Nailing 12/5/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 6/2/2026 Approved MICHEL ABAJAN
Final 6/2/2026 Corrections Issued MICHEL ABAJAN
Green Building Final 6/2/2026 Approved MICHEL ABAJAN
HVAC-Final 6/2/2026 Approved MICHEL ABAJAN
PLUMBING-Final 6/2/2026 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/2/2026 SGSOV Not Required MICHEL ABAJAN
Service/Power Release 6/2/2026 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 6/2/2026 Approved MICHEL ABAJAN
Service/Power Release 6/22/2026 Approved MICHEL ABAJAN
Final 7/13/2026 OK to Issue CofO MICHEL ABAJAN