23836 W VICTORY BLVD 91367

Certificate Information: 23836 W VICTORY BLVD 91367

Application / Permit
25010-20000-02081
Plan Check / Job No.
B25VN13413
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. (N) 1-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 6/3/2025
Issuing Office
Current Status
CofO Corrected on 2/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2025 APPLICANT
Assigned to Plan Check Engineer 5/19/2025 DANIEL YIP
Corrections Issued 5/20/2025 DANIEL YIP
Applicant returned to address corrections 5/27/2025 ADAM HEGAZI
Plan Check Approved 6/3/2025 DANIEL YIP
Issued 6/3/2025 APPLICANT
CofO in Progress 10/2/2025 GEVORK IPCHYAN
CofO Issued-Status Void 10/14/2025 JOHN JANSON
Permit Finaled-Status Void 10/14/2025 JOHN JANSON
Re-Activate Permit 2/3/2026 JOHN JANSON
Permit Finaled 2/3/2026 JOHN JANSON
CofO Corrected 2/3/2026 JOHN JANSON
Permit Finaled 2/3/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/22/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 5/22/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/23/2025 RYAN CASTRO
Sewer availability Cleared 5/23/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/16/2025 Not Ready for Inspection GEVORK IPCHYAN
Underground Mechanical 6/18/2025 Approved GEVORK IPCHYAN
Excavation/Setback/Form/Re-Bar 6/24/2025 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 6/24/2025 Corrections Issued JEFFREY HARTLINE
ELECTRICAL-Rough 7/15/2025 Approved GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/15/2025 Partial Approval GEVORK IPCHYAN
HVAC-Rough 7/15/2025 Approved GEVORK IPCHYAN
PLUMBING-Rough 7/15/2025 Approved GEVORK IPCHYAN
Wood Frame 7/15/2025 Approved GEVORK IPCHYAN
Insulation 7/21/2025 Approved TROY SANDERS
Interior/Exterior Lathing 7/21/2025 Partial Approval TROY SANDERS
Shower Pan 7/21/2025 Approved TROY SANDERS
Interior/Exterior Lathing 7/24/2025 Approved ROBERT GOLD
Drywall Nailing 7/29/2025 Approved GEVORK IPCHYAN
Green Building Rough 7/29/2025 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 9/29/2025 Approved GEVORK IPCHYAN
ELECTRICAL-Final 9/29/2025 Not Ready for Inspection GEVORK IPCHYAN
Final 9/29/2025 Corrections Issued GEVORK IPCHYAN
Footing/Foundation/Slab 9/29/2025 Approved GEVORK IPCHYAN
Green Building Final 9/29/2025 Not Ready for Inspection GEVORK IPCHYAN
HVAC-Final 9/29/2025 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Final 9/29/2025 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 9/29/2025 SGSOV Approved GEVORK IPCHYAN
Service/Power Release 9/29/2025 Not Ready for Inspection GEVORK IPCHYAN
Smoke Detectors 9/29/2025 Approved GEVORK IPCHYAN
Verify Sprinkler Sign Off 9/29/2025 Approved GEVORK IPCHYAN
ELECTRICAL-Final 10/1/2025 Approved GEVORK IPCHYAN
Final 10/1/2025 OK to Issue CofO GEVORK IPCHYAN
Green Building Final 10/1/2025 Approved GEVORK IPCHYAN
PLUMBING-Final 10/1/2025 Approved GEVORK IPCHYAN
Service/Power Release 10/1/2025 Approved GEVORK IPCHYAN