804-806 E 76TH ST 90001

Certificate Information: 804-806 E 76TH ST 90001

Application / Permit
25010-20000-02080
Plan Check / Job No.
B25VN13395
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH COVERED PORCH AND ATTACHED CAR GARAGE PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
Permit Issued
Issued on 1/6/2026
Issuing Office
Current Status
Issued on 1/6/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/13/2025 APPLICANT
Assigned to Plan Check Engineer 5/15/2025 ALFRED RAMIREZ
Assigned to Zoning Architect 5/15/2025 BENNY WONG
Corrections Issued 5/18/2025 ALFRED RAMIREZ
Quality Review Completed 5/21/2025 STEVEN KIM
Plan Check Approved 12/12/2025 ALFRED RAMIREZ
No Progress 12/15/2025 ALFRED RAMIREZ
Plan Check Approved 12/15/2025 ALFRED RAMIREZ
Issued 1/6/2026 APPLICANT

Permit Application Clearance Information

Low Impact Development (LID) Cleared 6/5/2025 ERNEST TSE
Community Plan Implem. Overlay Cleared 6/18/2025 ANACANY HURTADO
Address approval Cleared 6/24/2025 DAVID LOPEZ
Community Plan Implem. Overlay Cleared 6/24/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 6/24/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 6/24/2025 DAVID LOPEZ
Sewer availability Cleared 6/24/2025 DAVID LOPEZ
Hydrant and Access approval Cleared 7/2/2025 LAVEON RIDER
Community Plan Implem. Overlay Cleared 9/19/2025 MIGUEL ORNELAS
Community Plan Implem. Overlay Cleared 10/7/2025 COLLINS ALLAN
SB8 RUD Cleared 10/16/2025 ASHLEY MEDINA
Community Plan Implem. Overlay Cleared 12/1/2025 RIDWAN HARDY
Zoning Plan Check Cleared 12/3/2025 BENNY WONG

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/20/2026 Approved JOHN QUINTANILLA
Footing/Foundation/Slab 1/20/2026 Approved JOHN QUINTANILLA
Deputy Reinf. Concrete 1/22/2026 Conditional Approval JOHN QUINTANILLA
Sewer 2/11/2026 Approved JOHN QUINTANILLA
Underground Mechanical 2/11/2026 Approved JOHN QUINTANILLA
Wood Frame 2/11/2026 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 2/13/2026 Approved JOHN QUINTANILLA
Insulation 2/13/2026 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 2/24/2026 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 3/12/2026 Approved JOHN QUINTANILLA
Deputy Wood Construction 3/16/2026 Conditional Approval JOHN QUINTANILLA
ELECTRICAL-Rough 3/23/2026 Approved LUIS CASTRO
PLUMBING-Rough 3/23/2026 Approved LUIS CASTRO
BUILDING-Rough-Frame 4/13/2026 Not Ready for Inspection JOHN QUINTANILLA
Green Building Rough 4/13/2026 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Rough 4/13/2026 Not Ready for Inspection JOHN QUINTANILLA
Verify Sprinkler Sign Off 4/13/2026 Not Ready for Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 4/15/2026 Partial Approval JOHN QUINTANILLA
Green Building Rough 4/15/2026 Approved JOHN QUINTANILLA
HVAC-Rough 4/15/2026 Approved JOHN QUINTANILLA
Verify Sprinkler Sign Off 4/15/2026 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 4/17/2026 Conditional Approval ALEJANDRO DE ARTOLA
Insulation 4/17/2026 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/28/2026 Approved JOHN QUINTANILLA
Drywall Nailing 4/28/2026 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 4/28/2026 Approved JOHN QUINTANILLA