11419 W BOLAS ST 90049

Certificate Information: 11419 W BOLAS ST 90049

Application / Permit
25010-20000-02072
Plan Check / Job No.
B25VN13305
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 58'-0" X 39'-6" IRREGULAR SHAPED SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13D FIRE SPRINKLERED THROUGHOUT
Permit Issued
Issued on 10/8/2025
Issuing Office
Current Status
Issued on 10/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/12/2025 APPLICANT
Assigned to Zoning Architect 5/29/2025 ELAHE MERRIKHI
Assigned to Plan Check Engineer 6/5/2025 DANIEL ABRAMYAN
Corrections Issued 6/16/2025 DANIEL ABRAMYAN
Quality Review Completed 6/17/2025 OMID HEDAYAT
Building Plans Picked Up 6/20/2025 APPLICANT
Plan Check Approved 9/9/2025 SELLA BENYAMIN
Issued 10/8/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/3/2025 JESUS CISNEROS
Sewer availability Cleared 7/3/2025 JESUS CISNEROS
Eng Process Fee Ord 176,300 Cleared 7/7/2025 JESUS CISNEROS
ZA Case Cleared 7/7/2025 MATHEW QUAN
Hydrant and Access approval Cleared 7/9/2025 KURT CORRAL
Roof/Waste drainage to street Cleared 7/26/2025 JESUS CISNEROS
Specific Plan Cleared 7/28/2025 MOHAMMAD HASAN
Permit Cleared 8/19/2025 JESUS CISNEROS
Trees in Parkway Cleared 8/19/2025 RICHARD SANCHEZ
Zoning Plan Check Cleared 8/27/2025 ELAHE MERRIKHI
GPI Written Notices Cleared 9/9/2025 DANIEL ABRAMYAN
Grading Pre-Inspection Cleared 9/9/2025 DANIEL ABRAMYAN

Contact Information

Architect Lee,, Kenneth David; Lic. No.: C10141 16501 ACADEMIA DRIVE      ENCINO, CA 91436
Contractor Kdl Construction; Lic. No.: 1100757-B 16501 ACADEMIA DRIVE      ENCINO, CA 91436
Engineer Shakiban,, George; Lic. No.: C39908 23945 CALABASAS RD STE 101      CALABASAS, CA 91302

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/5/2025 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 11/5/2025 Approved CARLOS MATAMOROS
METHANE-Barrier 11/5/2025 Approved CARLOS MATAMOROS
METHANE-Rough 11/5/2025 Approved CARLOS MATAMOROS
METHANE-Subgrade 11/5/2025 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 11/24/2025 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 11/24/2025 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 1/9/2026 Partial Approval EVAN COOPER
ELECTRICAL-Rough 2/9/2026 Approved EVAN COOPER
HVAC-Rough 2/9/2026 Approved EVAN COOPER
PLUMBING-Rough 2/9/2026 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/4/2026 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Wood Construction 3/5/2026 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/5/2026 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 4/1/2026 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 4/1/2026 Corrections Issued CHRISTOPHER WILSON
Interior/Exterior Lathing 4/1/2026 Partial Approval CHRISTOPHER WILSON
MERV13>=Rough 4/1/2026 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 4/1/2026 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 4/9/2026 Approved EVAN COOPER
Green Building Rough 4/9/2026 Approved EVAN COOPER
MERV13>=Rough 4/9/2026 Approved EVAN COOPER
Shower Pan 4/9/2026 Approved EVAN COOPER
Green Building Rough 4/16/2026 Approved CHRISTOPHER WILSON
Insulation 4/16/2026 Approved CHRISTOPHER WILSON
Drywall Nailing 4/24/2026 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 4/24/2026 Approved CHRISTOPHER WILSON