8532 N NESTLE AVE 91325
Certificate Information: 8532 N NESTLE AVE 91325
- Application / Permit
- 25010-20000-02061
- Plan Check / Job No.
- B25VN13245
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: New detached 1-story ADU per LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k)
- Permit Issued
- Issued on 8/27/2025
- Issuing Office
- Current Status
- Issued on 8/27/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/29/2025 | DAVID CASTILLO |
| Corrections Issued | 5/30/2025 | DAVID CASTILLO |
| Plan Check Approved | 8/23/2025 | DAVID CASTILLO |
| Issued | 8/27/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/16/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 6/16/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 6/16/2025 | MICHAEL BROWN |
| Construction within easement | Cleared | 8/19/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nguyen,, Chuc Ich; Lic. No.: NA38556 | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Pre-Inspection | 6/8/2026 |
Inspection Request History
| PLUMBING-Rough | 1/14/2026 | Partial Approval | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 1/28/2026 | Not Ready for Inspection | KRISTEN CAUSEY |
| Deputy Reinf. Concrete | 2/6/2026 | Conditional Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 2/9/2026 | Approved | KRISTEN CAUSEY |
| Excavation/Setback/Form/Re-Bar | 4/21/2026 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2026 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2026 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2026 | Corrections Issued | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2026 | Corrections Issued | TROY SANDERS |
| Pre-Inspection | 5/29/2026 | Approved | TROY SANDERS |