6603 N DENSMORE AVE 91406

Certificate Information: 6603 N DENSMORE AVE 91406

Application / Permit
25010-20000-02060
Plan Check / Job No.
B25VN13241
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: Conversion of existing Detached garage into ADU Per State Law and GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 7/16/2025
Issuing Office
Current Status
CofO Issued on 3/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2025 APPLICANT
Assigned to Plan Check Engineer 5/19/2025 ZAW HAN
Corrections Issued 5/20/2025 ZAW HAN
Applicant returned to address corrections 6/9/2025 ZAW HAN
Applicant returned to address corrections 6/14/2025 ZAW HAN
Applicant returned to address corrections 7/7/2025 ZAW HAN
Plan Check Approved 7/8/2025 ZAW HAN
Issued 7/16/2025 APPLICANT
CofO in Progress 2/27/2026 GAREN HAYRAPETYAN
Permit Finaled 3/13/2026 RUBEN SALAS
CofO Issued 3/13/2026 RUBEN SALAS
Permit Finaled 3/13/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/28/2025 MICHAEL BROWN
Sewer availability Cleared 5/28/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 5/29/2025 MICHAEL BROWN
ZI Cleared 5/30/2025 FIPE LEILUA
Construction near power lines Cleared 7/3/2025 GEVORK KARAPETYAN
Construction within easement Cleared 7/3/2025 GEVORK KARAPETYAN
Roof/Waste drainage to street Cleared 7/3/2025 MICHAEL BROWN

Contact Information

Contractor A+ Local Garage Door Repair; Lic. No.: 1064628-B       ,
Contractor David Star Construction Inc; Lic. No.: 1064628-B       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/29/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 7/29/2025 Partial Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 8/4/2025 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 8/5/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 8/14/2025 Conditional Approval GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 8/14/2025 Corrections Issued GAREN HAYRAPETYAN
HVAC-Rough 8/14/2025 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 8/14/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 8/18/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 8/18/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/25/2025 Not Ready for Inspection WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 8/25/2025 Approved WILLIAM WREN
HVAC-Rough 8/25/2025 Approved WILLIAM WREN
Insulation 8/27/2025 Approved WAYNE REGESTER
Interior/Exterior Lathing 8/27/2025 Approved WAYNE REGESTER
Underground Mechanical 8/27/2025 Approved WAYNE REGESTER
Drywall Nailing 8/29/2025 Approved WAYNE REGESTER
Sewer 8/29/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 10/22/2025 Approved GAREN HAYRAPETYAN
Final 10/22/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 10/22/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 10/22/2025 Approved GAREN HAYRAPETYAN
MERV13>=Final 10/22/2025 Approved GAREN HAYRAPETYAN
MERV13>=Rough 10/22/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 10/22/2025 SGSOV Not Ready GAREN HAYRAPETYAN
Smoke Detectors 10/22/2025 Approved GAREN HAYRAPETYAN
Final 1/6/2026 Not Ready for Inspection GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 1/6/2026 SGSOV Not Ready GAREN HAYRAPETYAN
Final 1/16/2026 Not Ready for Inspection GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 1/16/2026 SGSOV Approved GAREN HAYRAPETYAN
Final 2/27/2026 OK to Issue CofO GAREN HAYRAPETYAN