6603 N DENSMORE AVE 91406
Certificate Information: 6603 N DENSMORE AVE 91406
- Application / Permit
- 25010-20000-02060
- Plan Check / Job No.
- B25VN13241
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: Conversion of existing Detached garage into ADU Per State Law and GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 7/16/2025
- Issuing Office
- Current Status
- CofO Issued on 3/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2025 | ZAW HAN |
| Corrections Issued | 5/20/2025 | ZAW HAN |
| Applicant returned to address corrections | 6/9/2025 | ZAW HAN |
| Applicant returned to address corrections | 6/14/2025 | ZAW HAN |
| Applicant returned to address corrections | 7/7/2025 | ZAW HAN |
| Plan Check Approved | 7/8/2025 | ZAW HAN |
| Issued | 7/16/2025 | APPLICANT |
| CofO in Progress | 2/27/2026 | GAREN HAYRAPETYAN |
| Permit Finaled | 3/13/2026 | RUBEN SALAS |
| CofO Issued | 3/13/2026 | RUBEN SALAS |
| Permit Finaled | 3/13/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/28/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 5/28/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 5/29/2025 | MICHAEL BROWN |
| ZI | Cleared | 5/30/2025 | FIPE LEILUA |
| Construction near power lines | Cleared | 7/3/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 7/3/2025 | GEVORK KARAPETYAN |
| Roof/Waste drainage to street | Cleared | 7/3/2025 | MICHAEL BROWN |
Contact Information
| Contractor | A+ Local Garage Door Repair; Lic. No.: 1064628-B | , |
| Contractor | David Star Construction Inc; Lic. No.: 1064628-B | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 7/29/2025 | Partial Approval | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 8/4/2025 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 8/5/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 8/14/2025 | Conditional Approval | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| HVAC-Rough | 8/14/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 8/14/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 8/18/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 8/18/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/25/2025 | Not Ready for Inspection | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2025 | Approved | WILLIAM WREN |
| HVAC-Rough | 8/25/2025 | Approved | WILLIAM WREN |
| Insulation | 8/27/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 8/27/2025 | Approved | WAYNE REGESTER |
| Underground Mechanical | 8/27/2025 | Approved | WAYNE REGESTER |
| Drywall Nailing | 8/29/2025 | Approved | WAYNE REGESTER |
| Sewer | 8/29/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 10/22/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 10/22/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 10/22/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 10/22/2025 | Approved | GAREN HAYRAPETYAN |
| MERV13>=Final | 10/22/2025 | Approved | GAREN HAYRAPETYAN |
| MERV13>=Rough | 10/22/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 10/22/2025 | SGSOV Not Ready | GAREN HAYRAPETYAN |
| Smoke Detectors | 10/22/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 1/6/2026 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 1/6/2026 | SGSOV Not Ready | GAREN HAYRAPETYAN |
| Final | 1/16/2026 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 1/16/2026 | SGSOV Approved | GAREN HAYRAPETYAN |
| Final | 2/27/2026 | OK to Issue CofO | GAREN HAYRAPETYAN |