23305 W CALIFA ST 91367
Certificate Information: 23305 W CALIFA ST 91367
- Application / Permit
- 25010-20000-02053
- Plan Check / Job No.
- B25VN13169
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Detached ADU PER LAMC 12.22 A.33 (b)(1)
- Permit Issued
- Issued on 6/25/2025
- Issuing Office
- Current Status
- CofO in Progress on 3/31/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2025 | SUNMIN LEE |
| Corrections Issued | 5/15/2025 | SUNMIN LEE |
| Applicant returned to address corrections | 6/5/2025 | SUNMIN LEE |
| Applicant returned to address corrections | 6/9/2025 | SUNMIN LEE |
| Applicant returned to address corrections | 6/12/2025 | SUNMIN LEE |
| Applicant returned to address corrections | 6/16/2025 | SUNMIN LEE |
| Applicant returned to address corrections | 6/17/2025 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 6/19/2025 | ALEC MOUSAKHANIAN |
| Issued | 6/25/2025 | APPLICANT |
| CofO in Progress | 3/31/2026 | TROY SANDERS |
Permit Application Clearance Information
| ZA Case | Cleared | 5/15/2025 | JASON CHAN |
| Grading Pre-Inspection | Cleared | 5/17/2025 | ALEXANDER HELFER |
| Address approval | Cleared | 5/20/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 5/20/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 5/20/2025 | BIAINA HARITUNIAN |
| Construction within easement | Cleared | 6/4/2025 | TINA MIRANDA |
| GPI Written Notices | Cleared | 6/5/2025 | SUNMIN LEE |
Contact Information
| Contractor | Builders Hub Renovation Inc; Lic. No.: 1063741-B | , |
| Engineer | Boules,, George H; Lic. No.: NA64144 | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/18/2025 | Conditional Approval | TROY SANDERS |
| Special/Order Compliance | 7/18/2025 | Corrections Issued | TROY SANDERS |
| PLUMBING-Rough | 8/18/2025 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2025 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 9/22/2025 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2025 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 10/23/2025 | Approved | TROY SANDERS |
| PLUMBING-Rough | 10/23/2025 | Approved | TROY SANDERS |
| Sewer | 11/17/2025 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 12/23/2025 | Approved | TROY SANDERS |
| HVAC-Rough | 12/23/2025 | Approved | TROY SANDERS |
| PLUMBING-Rough | 12/23/2025 | Approved | TROY SANDERS |
| Insulation | 1/9/2026 | Conditional Approval | TROY SANDERS |
| Interior/Exterior Lathing | 1/9/2026 | Partial Approval | TROY SANDERS |
| Shower Pan | 1/9/2026 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 1/14/2026 | Corrections Issued | TROY SANDERS |
| Green Building Rough | 1/14/2026 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 1/14/2026 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 1/20/2026 | Approved | TROY SANDERS |
| Insulation | 1/20/2026 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 1/20/2026 | Partial Approval | TROY SANDERS |
| Verify Sprinkler Sign Off | 1/20/2026 | Approved | TROY SANDERS |
| Drywall Nailing | 1/21/2026 | Approved | TROY SANDERS |
| Final | 3/27/2026 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 3/27/2026 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 3/27/2026 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 3/27/2026 | Approved | TROY SANDERS |
| Smoke Detectors | 3/27/2026 | Approved | TROY SANDERS |