7248 N CALDUS AVE 91406
Certificate Information: 7248 N CALDUS AVE 91406
- Application / Permit
- 25010-20000-02003
- Plan Check / Job No.
- B25VN12878
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- [ePlan] NEW DETACHED 1-STORY ADU PER GC 66323(a)(2)
- Permit Issued
- Issued on 8/3/2025
- Issuing Office
- Current Status
- Issued on 8/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/29/2025 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 6/5/2025 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 6/10/2025 | SINA KHOSRAVI |
| Applicant returned to address corrections | 7/6/2025 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 7/10/2025 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 7/31/2025 | MAHNAZ NOURHASHEMI |
| Issued | 8/3/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/20/2025 | OSCAR CASTRO |
| Construction within easement | Cleared | 6/20/2025 | OSCAR CASTRO |
| Address approval | Cleared | 6/23/2025 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2025 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 6/23/2025 | JEANIE LAM |
| Sewer availability | Cleared | 6/23/2025 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christenson,, Paul Scott; Lic. No.: NA57182 | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/19/2025 | Corrections Issued | JACK KARGODORIAN |
| Underground Mechanical | 8/19/2025 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 9/12/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Excavation/Setback/Form/Re-Bar | 9/22/2025 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 9/22/2025 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 10/29/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2025 | Approved | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 11/13/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 12/5/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 12/5/2025 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 12/5/2025 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 12/10/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 12/10/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 12/10/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Insulation | 12/18/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 12/24/2025 | Approved | CRAIG DAVIS |
| Interior/Exterior Lathing | 12/24/2025 | Approved | CRAIG DAVIS |
| Final | 5/26/2026 | Corrections Issued | MICHAEL CORTEZ |
| SGSOV-Seismic Gas S/O Valve | 5/26/2026 | SGSOV Not Required | MICHAEL CORTEZ |
| Smoke Detectors | 5/26/2026 | Approved | MICHAEL CORTEZ |