19057 W SYLVAN ST 91335

Certificate Information: 19057 W SYLVAN ST 91335

Application / Permit
25010-20000-01995
Plan Check / Job No.
B25VN12848
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT WITH ATTACHED PORCH PER GC 66323(a)(2). WORK PER ENGINEERED DESIGN.
Permit Issued
Issued on 5/30/2025
Issuing Office
Current Status
Issued on 5/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/7/2025 APPLICANT
Assigned to Plan Check Engineer 5/15/2025 OMAR GARNICA
Corrections Issued 5/15/2025 OMAR GARNICA
Building Plans Picked Up 5/16/2025 APPLICANT
Plan Check Approved 5/30/2025 NAREG ATARIAN
Issued 5/30/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/22/2025 TAL SHEMEN
Construction near power lines Cleared 5/22/2025 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 5/22/2025 TAL SHEMEN
Roof/Waste drainage to street Cleared 5/22/2025 TAL SHEMEN
Sewer availability Cleared 5/22/2025 BIAINA HARITUNIAN
Public Works-Sewers Cleared 5/22/2025 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,
Engineer Amar,, David; Lic. No.: C97582 6160 CORBIN AVENUE      TARZANA, CA 91356

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Final 6/10/2026   
Footing/Foundation/Slab 6/10/2026   
Smoke Detectors 6/10/2026   
SGSOV-Seismic Gas S/O Valve 6/10/2026   
Green Building Final 6/10/2026   

Inspection Request History

Footing/Foundation/Slab 9/12/2025 Corrections Issued MORRIS JACKSON
PLUMBING-Rough 9/12/2025 Partial Approval MORRIS JACKSON
BUILDING-Rough-Frame 10/15/2025 Corrections Issued MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 10/15/2025 Partial Approval MORRIS JACKSON
BUILDING-Rough-Frame 10/22/2025 Not Ready for Inspection MORRIS JACKSON
Green Building Rough 10/22/2025 Not Ready for Inspection MORRIS JACKSON
Verify Sprinkler Sign Off 10/22/2025 Partial Inspection MORRIS JACKSON
Deputy Drilled-In Anchors 10/24/2025 Conditional Approval MORRIS JACKSON
Gas Test 11/5/2025 Approved MORRIS JACKSON
HVAC-Rough 11/5/2025 Approved MORRIS JACKSON
PLUMBING-Rough 11/5/2025 Approved MORRIS JACKSON
ELECTRICAL-Rough 11/26/2025 Approved MORRIS JACKSON
BUILDING-Rough-Frame 12/4/2025 Approved MORRIS JACKSON
Green Building Rough 12/4/2025 Approved MORRIS JACKSON
Insulation 12/10/2025 Approved MORRIS JACKSON
Shower Pan 12/24/2025 Approved JON MCHUGH
Special/Order Compliance 12/24/2025 Corrections Issued JON MCHUGH
Drywall Nailing 12/30/2025 Approved MORRIS JACKSON
Sewer 12/30/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 1/5/2026 Approved MORRIS JACKSON
Pre-Inspection 3/20/2026 Partial Inspection MORRIS JACKSON
Underground Mechanical 3/31/2026 Approved MORRIS JACKSON
Final 5/6/2026 Corrections Issued MORRIS JACKSON
Service/Power Release 5/6/2026 Approved MORRIS JACKSON