6436 N QUAKERTOWN AVE 91367
Certificate Information: 6436 N QUAKERTOWN AVE 91367
- Application / Permit
- 25010-20000-01993
- Plan Check / Job No.
- B25VN12836
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 29'-1" X 25'-5" DETACHED ACCESSORY DWELLING UNIT GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g) ; EQUIPPED WITH NFPA 13-D FIRE SPRINLERS THROUGHOUT
- Permit Issued
- Issued on 6/17/2025
- Issuing Office
- Current Status
- Issued on 6/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2025 | SELLA BENYAMIN |
| Corrections Issued | 5/12/2025 | SELLA BENYAMIN |
| Quality Review Completed | 5/12/2025 | STEVEN KIM |
| Building Plans Picked Up | 5/13/2025 | APPLICANT |
| Plan Check Approved | 6/17/2025 | SELLA BENYAMIN |
| Issued | 6/17/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/16/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 5/16/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 5/19/2025 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 6/13/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Amar,, David; Lic. No.: C97582 | 6160 CORBIN AVENUE TARZANA, CA 91356 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/2/2025 | Partial Approval | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 9/10/2025 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 9/10/2025 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2025 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 10/31/2025 | Approved | JON MCHUGH |
| HVAC-Rough | 10/31/2025 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 10/31/2025 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 11/7/2025 | Partial Approval | DAVID SCANTLIN |
| PLUMBING-Rough | 11/13/2025 | Approved | ALEXANDER HANDY |
| Shower Pan | 12/1/2025 | Approved | JUAN ALVARADO |
| Shower Pan | 12/2/2025 | Partial Inspection | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2025 | Partial Approval | ALEXANDER HANDY |
| Interior/Exterior Lathing | 12/23/2025 | Partial Approval | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 12/29/2025 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 1/21/2026 | Corrections Issued | ALEXANDER HANDY |
| Green Building Rough | 1/21/2026 | Approved | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 1/21/2026 | Approved | ALEXANDER HANDY |
| Insulation | 1/23/2026 | Corrections Issued | ALEXANDER HANDY |
| Insulation | 1/27/2026 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 2/9/2026 | Approved | DAVID FASTIGGI |
| Underground Mechanical | 2/25/2026 | Approved | DAVID FASTIGGI |
| Underground Mechanical | 3/5/2026 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 7/10/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Final | 7/10/2026 | Corrections Issued | ALEXANDER HANDY |
| Final | 7/10/2026 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 7/10/2026 | Approved | ALEXANDER HANDY |
| HVAC-Final | 7/10/2026 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 7/10/2026 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 7/10/2026 | SGSOV No Gas | ALEXANDER HANDY |
| Service/Power Release | 7/10/2026 | Not Required | ALEXANDER HANDY |
| Smoke Detectors | 7/10/2026 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 7/17/2026 | Not Ready for Inspection | ROBERT GOLD |
| HVAC-Final | 7/17/2026 | Approved | ROBERT GOLD |
| PLUMBING-Final | 7/17/2026 | Approved | ROBERT GOLD |
| Service/Power Release | 7/17/2026 | Not Required | ROBERT GOLD |