4703 1/2 N KRAFT AVE 91602

Certificate Information: 4703 1/2 N KRAFT AVE 91602

Application / Permit
25010-20000-01991
Plan Check / Job No.
B25VN12810
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN-NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k). ALL WORK PER ENG.
Permit Issued
Issued on 7/25/2025
Issuing Office
Current Status
CofO Issued on 12/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2025 APPLICANT
Assigned to Plan Check Engineer 5/12/2025 ARAMIK SHAHMIRZAIAN
Corrections Issued 5/13/2025 ARAMIK SHAHMIRZAIAN
Applicant returned to address corrections 7/10/2025 LUISANGEL VALENZUELA
Plan Check Approved 7/17/2025 PINANK PATEL
Issued 7/25/2025 APPLICANT
CofO in Progress 11/26/2025 JAVIER RAMOS JR
Permit Finaled 12/26/2025 RUBEN SALAS
Permit Finaled 12/26/2025 RUBEN SALAS
CofO Issued 12/26/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/29/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/30/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/30/2025 BIAINA HARITUNIAN
Sewer availability Cleared 5/30/2025 BIAINA HARITUNIAN
Specific Plan Cleared 6/20/2025 JOANNA MARROQUIN
Construction near power lines Cleared 7/9/2025 GEVORK KARAPETYAN

Contact Information

Contractor Cedars Design & Remodeling Inc; Lic. No.: 1031288-B       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/6/2025 Partial Approval MISAEL ESPARZA
Sewer 8/6/2025 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 8/8/2025 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 8/8/2025 Not Ready for Inspection JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 8/15/2025 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 8/15/2025 Corrections Issued JAVIER RAMOS JR
Deputy Drilled-In Anchors 8/19/2025 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 8/19/2025 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 9/3/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 9/3/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 9/3/2025 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 9/3/2025 Partial Inspection JAVIER RAMOS JR
PLUMBING-Rough 9/3/2025 Approved JAVIER RAMOS JR
Underground Mechanical 9/3/2025 Partial Approval JAVIER RAMOS JR
Deputy Wood Construction 9/4/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Approved JAVIER RAMOS JR
HVAC-Rough 9/11/2025 Approved JAVIER RAMOS JR
Insulation 9/11/2025 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 9/11/2025 Partial Approval JAVIER RAMOS JR
Underground Mechanical 9/11/2025 Approved JAVIER RAMOS JR
Drywall Nailing 9/16/2025 Corrections Issued JAVIER RAMOS JR
Insulation 9/16/2025 Partial Approval JAVIER RAMOS JR
Interior/Exterior Lathing 9/22/2025 Approved JAVIER RAMOS JR
Shower Pan 9/22/2025 Approved JAVIER RAMOS JR
Drywall Nailing 10/1/2025 Not Ready for Inspection LOUIS ESCOTO
Drywall Nailing 10/8/2025 Approved MICHAEL CORTEZ
BUILDING-Rough-Frame 10/15/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 10/15/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 10/15/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 10/15/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 10/15/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
MERV13>=Final 10/15/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
MERV13>=Rough 10/15/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 10/15/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 10/15/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 10/15/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 10/21/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Final 10/21/2025 Corrections Issued JAVIER RAMOS JR
Final 10/21/2025 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 10/21/2025 Approved JAVIER RAMOS JR
Green Building Final 10/21/2025 Approved JAVIER RAMOS JR
Green Building Rough 10/21/2025 Approved JAVIER RAMOS JR
HVAC-Final 10/21/2025 Approved JAVIER RAMOS JR
MERV13>=Final 10/21/2025 Approved JAVIER RAMOS JR
MERV13>=Rough 10/21/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 10/21/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 10/21/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 10/21/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 10/24/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 10/24/2025 Approved JAVIER RAMOS JR
Final 10/24/2025 Corrections Issued JAVIER RAMOS JR
Final 11/25/2025 OK to Issue CofO JAVIER RAMOS JR