12389 W SHELDON ST 91352
Certificate Information: 12389 W SHELDON ST 91352
- Application / Permit
- 25010-20000-01949
- Plan Check / Job No.
- B25VN12458
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU per gc 66323(a)(2)
- Permit Issued
- Issued on 6/2/2025
- Issuing Office
- Current Status
- Issued on 6/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2025 | SHANGQIN XIE |
| Corrections Issued | 5/12/2025 | SHANGQIN XIE |
| Plan Check Approved | 5/19/2025 | SHANGQIN XIE |
| Issued | 6/2/2025 | APPLICANT |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 5/13/2025 | RUBEN VASQUEZ |
| Address approval | Cleared | 5/15/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 5/16/2025 | TREVOR QUAN |
| Sewer availability | Cleared | 5/16/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/4/2025 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 6/4/2025 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 6/11/2025 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 6/11/2025 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/28/2025 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/28/2025 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 7/28/2025 | Approved | MATTHEW NELSON |
| HVAC-Rough | 7/28/2025 | Approved | MATTHEW NELSON |
| MERV13>=Rough | 7/28/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 7/28/2025 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 7/28/2025 | Partial Inspection | MATTHEW NELSON |
| Wood Frame | 7/28/2025 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/1/2025 | Partial Approval | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/1/2025 | Partial Approval | MATTHEW NELSON |
| Insulation | 8/7/2025 | Approved | MATTHEW NELSON |
| Shower Pan | 8/7/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Drywall Nailing | 8/12/2025 | Approved | STUART CHAPMAN |
| Shower Pan | 8/12/2025 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 8/20/2025 | Approved | MICHAEL CORTEZ |
| Sewer | 9/3/2025 | Approved | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 9/12/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Underground Mechanical | 9/12/2025 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/30/2025 | Approved | MATTHEW NELSON |
| Final | 10/30/2025 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 10/30/2025 | Corrections Issued | MATTHEW NELSON |
| MERV13>=Final | 10/30/2025 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 10/30/2025 | SGSOV Not Required | MATTHEW NELSON |
| Service/Power Release | 10/30/2025 | Corrections Issued | MATTHEW NELSON |
| Smoke Detectors | 10/30/2025 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 10/30/2025 | Approved | MATTHEW NELSON |
| Final | 12/17/2025 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 12/17/2025 | Corrections Issued | MATTHEW NELSON |
| Service/Power Release | 12/17/2025 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Final | 12/23/2025 | Not Ready for Inspection | CRAIG DAVIS |