9707 N WILLIS AVE 91343
Certificate Information: 9707 N WILLIS AVE 91343
- Application / Permit
- 25010-20000-01930
- Plan Check / Job No.
- B25VN12404
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New detached 2-story accessory dwelling unit PER LAMC 12.22 A.33(b)(1)3 at rear of lot
- Permit Issued
- Issued on 8/20/2025
- Issuing Office
- Current Status
- Issued on 8/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2025 | JAD BASMA |
| Corrections Issued | 5/10/2025 | JAD BASMA |
| Quality Review Completed | 5/21/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 8/5/2025 | JAD BASMA |
| Plan Check Approved | 8/12/2025 | JAD BASMA |
| Issued | 8/20/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/18/2025 | GEVORK KARAPETYAN |
| Address approval | Cleared | 7/25/2025 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 7/25/2025 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2025 | JEANIE LAM |
| Sewer availability | Cleared | 7/31/2025 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/25/2025 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 8/29/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/8/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Rough | 9/8/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 9/8/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/10/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 9/10/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 9/10/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Deputy Wood Construction | 9/11/2025 | No Result Entered | JOHN COLEMAN |
| BUILDING-Rough-Frame | 9/12/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 9/12/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 9/12/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/30/2025 | Approved | JENNIFER RABUCHIN |
| Sewer | 9/30/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/2/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 10/2/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/7/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 10/7/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/16/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/16/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/16/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 10/21/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/24/2025 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/28/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/29/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 10/29/2025 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 10/29/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 10/31/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 11/6/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 11/6/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 11/10/2025 | Approved | CHRISTOPHER MORFIN |
| HVAC-Rough | 1/23/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Underground Mechanical | 1/23/2026 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/5/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/5/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 2/5/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 2/5/2026 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 2/5/2026 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/5/2026 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/5/2026 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 2/5/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 2/5/2026 | Approved | JENNIFER RABUCHIN |
| Final | 2/24/2026 | Not Ready for Inspection | JOSE AVILA |
| ELECTRICAL-Final | 3/6/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 3/6/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 3/6/2026 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 3/6/2026 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/6/2026 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 3/6/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 5/21/2026 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/21/2026 | SGSOV Not Required | JENNIFER RABUCHIN |
| Service/Power Release | 5/21/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |