7744 N VASSAR AVE 91304

Certificate Information: 7744 N VASSAR AVE 91304

Application / Permit
25010-20000-01929
Plan Check / Job No.
B25VN12398
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY DETACHED 2ND DWELLING UNIT PER SB9 TWO-UNIT DEVELOPMENT PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
Permit Issued
Issued on 7/10/2025
Issuing Office
Current Status
CofO Issued on 4/18/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2025 APPLICANT
Assigned to Plan Check Engineer 5/8/2025 ALFRED RAMIREZ
Corrections Issued 5/11/2025 ALFRED RAMIREZ
Quality Review Completed 5/12/2025 STEVEN KIM
Building Plans Picked Up 5/12/2025 APPLICANT
Applicant returned to address corrections 5/30/2025 ALFRED RAMIREZ
Applicant returned to address corrections 6/11/2025 ALFRED RAMIREZ
Plan Check Approved 7/10/2025 ALFRED RAMIREZ
Issued 7/10/2025 APPLICANT
CofO in Progress 3/20/2026 ALEXANDER HANDY
Permit Finaled 4/18/2026 MICHAEL PELHAM
CofO Issued 4/18/2026 MICHAEL PELHAM
Permit Finaled 4/18/2026 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 5/12/2025 COLIN LOREDO
Roof/Waste drainage to street Cleared 5/12/2025 COLIN LOREDO
Tract Map conditions Cleared 5/13/2025 JASON CHAN
ZI Cleared 5/13/2025 JASON CHAN
Hydrant and Access approval Cleared 5/22/2025 FRANK GOMEZ
Senate Bill 9 Cleared 5/23/2025 JASON CHAN
Eng Process Fee Ord 176,300 Cleared 6/26/2025 RYAN CASTRO
Sewer availability Cleared 6/26/2025 RYAN CASTRO

Contact Information

Contractor Trinity Builders & Design Inc; Lic. No.: 988119-B 7022 DARBY AVE UNIT A      RESEDA, CA 91335
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/27/2025 Approved ALEXANDER HANDY
METHANE-Barrier 8/27/2025 Not Ready for Inspection ALEXANDER HANDY
METHANE-Subgrade 8/27/2025 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Rough 8/27/2025 Partial Approval ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 9/12/2025 Partial Approval ALEXANDER HANDY
Deputy Wood Construction 10/10/2025 Conditional Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 10/10/2025 Corrections Issued MORRIS JACKSON
ELECTRICAL-Rough 10/28/2025 Approved ALEXANDER HANDY
HVAC-Rough 10/28/2025 Approved ALEXANDER HANDY
PLUMBING-Rough 10/28/2025 Corrections Issued ALEXANDER HANDY
Interior/Exterior Lathing 10/30/2025 Partial Approval ALEXANDER HANDY
Shower Pan 10/30/2025 Approved ALEXANDER HANDY
Underground Mechanical 11/6/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 11/12/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 11/14/2025 Approved ALEXANDER HANDY
Green Building Rough 11/14/2025 Approved ALEXANDER HANDY
METHANE-Rough 11/14/2025 Approved ALEXANDER HANDY
Verify Sprinkler Sign Off 11/14/2025 Approved ALEXANDER HANDY
Drywall Nailing 11/24/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 2/25/2026 Corrections Issued ALEXANDER HANDY
PLUMBING-Final 2/25/2026 Approved ALEXANDER HANDY
Final 3/17/2026 OK to Issue CofO ALEXANDER HANDY
Green Building Final 3/17/2026 Approved ALEXANDER HANDY
HVAC-Final 3/17/2026 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 3/17/2026 SGSOV Approved ALEXANDER HANDY
Service/Power Release 3/17/2026 Not Required ALEXANDER HANDY
Smoke Detectors 3/17/2026 Approved ALEXANDER HANDY