940 N KAGAWA ST 90272
Certificate Information: 940 N KAGAWA ST 90272
- Application / Permit
- 25010-20000-01925
- Plan Check / Job No.
- B25VN12380
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 6/10/2025
- Issuing Office
- Valley
- Current Status
- Issued on 6/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2025 | SELLA BENYAMIN |
| Corrections Issued | 5/8/2025 | SELLA BENYAMIN |
| Quality Review Completed | 5/9/2025 | STEVEN KIM |
| Building Plans Picked Up | 5/9/2025 | APPLICANT |
| Plan Check Approved | 6/10/2025 | SELLA BENYAMIN |
| Issued | 6/10/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 5/12/2025 | SAFA JAVANMARDI |
| Hydrant and Access approval | Cleared | 5/29/2025 | JERRY KAO |
| Roof/Waste drainage to street | Cleared | 6/2/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Saridakis Kostandinos; Lic. No.: 1007393-B | 2800 28TH ST STE 133 SANTA MONICA, CA 90405 |
| Engineer | Namvar,, Mohammad Alipour; Lic. No.: C39797 | 231 VISTA DEL MAR STE D REDONDO BEACH, CA 90277 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/11/2025 | Conditional Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 8/20/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Deputy Shotcrete | 8/22/2025 | Conditional Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 8/27/2025 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 9/2/2025 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Reinf. Concrete | 9/3/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Deputy Drilled-In Anchors | 9/29/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Deputy Steel/Welding | 10/1/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 10/6/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2025 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2025 | Not Ready for Inspection | BOBBY KEY |
| Special/Order Compliance | 12/29/2025 | Partial Inspection | DAVID FASTIGGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2025 | Partial Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2026 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 2/19/2026 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 2/19/2026 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 2/19/2026 | Corrections Issued | TEMISTOCLES CAAL |
| Shower Pan | 2/19/2026 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 2/24/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| HVAC-Rough | 2/24/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 2/24/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 2/25/2026 | Partial Approval | DANIEL VERA |
| ELECTRICAL-Rough | 3/2/2026 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 3/2/2026 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Rough | 3/2/2026 | Corrections Issued | DANIEL VERA |
| BUILDING-Rough-Frame | 3/10/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 3/10/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Green Building Rough | 3/10/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| HVAC-Rough | 3/10/2026 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 3/10/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 3/10/2026 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 3/13/2026 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 3/13/2026 | Not Ready for Inspection | DANIEL VERA |
| Green Building Rough | 3/13/2026 | Approved | DANIEL VERA |
| PLUMBING-Rough | 3/13/2026 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 3/20/2026 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 3/20/2026 | Conditional Approval | RYAN SALAZAR |
| Insulation | 3/27/2026 | Corrections Issued | MICHAEL ALLEN |
| Interior/Exterior Lathing | 4/3/2026 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 4/22/2026 | Approved | TEMISTOCLES CAAL |