15530-15532 W BOWDOIN ST 90272
Certificate Information: 15530-15532 W BOWDOIN ST 90272
- Application / Permit
- 25010-20000-01923
- Plan Check / Job No.
- B25VN12377
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE AND ADU GCS 66323(a)(1). NFPA 13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 9/23/2025
- Issuing Office
- Current Status
- Issued on 9/23/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2025 | RAPHAEL ROSAS |
| Corrections Issued | 5/8/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 5/9/2025 | STEVEN KIM |
| Building Plans Picked Up | 5/9/2025 | APPLICANT |
| Plan Check Approved | 7/15/2025 | RAPHAEL ROSAS |
| Issued | 9/23/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/7/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2025 | SAFA JAVANMARDI |
| Low Impact Development (LID) | Cleared | 5/7/2025 | SARAH YOUSSEF |
| Sewer availability | Cleared | 5/7/2025 | SAFA JAVANMARDI |
| Hydrant and Access approval | Cleared | 5/15/2025 | KURT CORRAL |
| Construction near power lines | Cleared | 5/28/2025 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 6/9/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Birdwell / Peck Construction Llc; Lic. No.: 911863-B | 11524 BELLAGIO ROAD LOS ANGELES, CA 90049 |
| Engineer | Cattan,, Christian George; Lic. No.: C82566 | 8444 OWENSMOUTH AVE CANOGA PARK, CA 91304 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/30/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| Pre-Inspection | 10/30/2025 | Partial Inspection | STEPHANIE SWANSON |
| PLUMBING-Rough | 12/18/2025 | Partial Approval | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 1/15/2026 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 1/15/2026 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 1/21/2026 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2026 | Partial Approval | STEPHANIE SWANSON |
| Light Gage Steel Frame | 3/18/2026 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2026 | Approved | MICHAEL ALLEN |
| Green Building Rough | 5/8/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| Structural Steel Frame | 5/8/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 5/8/2026 | Not Ready for Inspection | MICHAEL ALLEN |