10113 N TOPEKA DR 91324
Certificate Information: 10113 N TOPEKA DR 91324
- Application / Permit
- 25010-20000-01908
- Plan Check / Job No.
- B25VN12237
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: (N) 792 SF NEW DETACHED ADU 2 BED 1 BATH PER GC 66323(a)(2)
- Permit Issued
- Issued on 10/3/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/26/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2025 | NGHI SU |
| Corrections Issued | 5/13/2025 | NGHI SU |
| Plan Check Approved | 6/4/2025 | TSE MING HUANG |
| Issued | 10/3/2025 | APPLICANT |
| CofO in Progress | 5/20/2026 | JACK KARGODORIAN |
| No Progress | 5/26/2026 | CHRISTOPHER WILSON |
| CofO in Progress | 5/26/2026 | CHRISTOPHER WILSON |
| CofO in Progress | 5/26/2026 | JACK KARGODORIAN |
Permit Application Clearance Information
| Address approval | Cleared | 5/19/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 5/19/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 5/28/2025 | DAVID LOPEZ |
| Hydrant and Access approval | Cleared | 5/29/2025 | FRANK GOMEZ |
Contact Information
| Contractor | Vando Construction; Lic. No.: 1122029-B | , |
| Engineer | Hernandez, Sotomayor, Daniel; Lic. No.: C93095 | 15755 SATICOY ST APT#306 VAN NUYS, CA 91406 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/20/2025 | Partial Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 10/23/2025 | Conditional Approval | KRISTEN CAUSEY |
| Deputy Reinf. Concrete | 10/24/2025 | Conditional Approval | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 10/24/2025 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 11/7/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2025 | Partial Approval | DAVID SCANTLIN |
| Green Building Rough | 11/7/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 11/7/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Wood Frame | 11/7/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 11/13/2025 | Corrections Issued | DAVID SCANTLIN |
| Green Building Rough | 11/13/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 11/13/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Deputy Wood Construction | 11/14/2025 | Conditional Approval | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 11/24/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 11/24/2025 | Approved | DAVID SCANTLIN |
| Green Building Rough | 11/24/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 11/24/2025 | Approved | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 11/24/2025 | Partial Approval | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 11/24/2025 | Approved | DAVID SCANTLIN |
| Wood Frame | 11/24/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 12/2/2025 | Approved | DAVID SCANTLIN |
| Green Building Rough | 12/2/2025 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 12/2/2025 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 12/2/2025 | Partial Approval | DAVID SCANTLIN |
| Insulation | 12/5/2025 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 12/5/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Shower Pan | 12/5/2025 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 1/6/2026 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 1/6/2026 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 3/27/2026 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 4/14/2026 | Approved | DAVID SCANTLIN |
| Final | 5/5/2026 | Corrections Issued | DAVID SCANTLIN |
| Footing/Foundation/Slab | 5/5/2026 | Approved | DAVID SCANTLIN |
| Green Building Final | 5/5/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 5/5/2026 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 5/5/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 5/5/2026 | Approved | DAVID SCANTLIN |
| Final | 5/20/2026 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Final | 5/20/2026 | Approved | JACK KARGODORIAN |
| Service/Power Release | 5/20/2026 | Approved | JACK KARGODORIAN |
| Final | 5/26/2026 | Corrections Issued | JACK KARGODORIAN |