eplan NEW TWO STORY DUPLEX WITH TWO ATTACHED TWO CAR GARAGE AND ONE CAR GARAGE , NFPA-13D SPRINKLERED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 10/8/2025
Issuing Office
Current Status
CofO Issued on 4/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2025 APPLICANT
Assigned to Plan Check Engineer 5/15/2025 RARES BODEA
Corrections Issued 5/22/2025 DANIEL ABRAMYAN
Quality Review Completed 5/22/2025 OMID HEDAYAT
Assigned to Zoning Architect 5/22/2025 DAVID ZHENG
Applicant returned to address corrections 9/24/2025 RARES BODEA
Plan Check Approved 10/3/2025 RARES BODEA
Issued 10/8/2025 APPLICANT
CofO in Progress 4/6/2026 SABAS ALONSO
Permit Finaled 4/7/2026 DEROLD HAUFF
CofO Issued 4/7/2026 DEROLD HAUFF
Permit Finaled 4/7/2026 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development (LID) Cleared 6/5/2025 ERNEST TSE
Historic Resource Verification Cleared 6/12/2025 RAFAEL FONTES
Address approval Cleared 6/18/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 6/18/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/20/2025 BIAINA HARITUNIAN
Sewer availability Cleared 6/20/2025 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 7/2/2025 JOHN CONNEALLY
Redevelopment Project Area Cleared 7/7/2025 YASMINE BASHIRI
SB8 RUD Cleared 9/11/2025 ALYSSA FLORES
Zoning Plan Check Cleared 9/17/2025 DAVID ZHENG

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 11/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 11/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 11/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/14/2025 Partial Approval ALEJANDRO DE ARTOLA
Sewer 11/14/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 11/14/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/20/2025 Partial Inspection ALEJANDRO DE ARTOLA
Insulation 11/20/2025 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/26/2025 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/16/2025 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 1/9/2026 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 1/9/2026 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/14/2026 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 1/14/2026 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/14/2026 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 1/14/2026 Not Ready for Inspection ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/15/2026 Corrections Issued WILLIAM SIERRA
Green Building Rough 1/15/2026 Approved WILLIAM SIERRA
PLUMBING-Rough 1/15/2026 Approved WILLIAM SIERRA
Verify Sprinkler Sign Off 1/15/2026 Approved WILLIAM SIERRA
Insulation 1/20/2026 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 1/20/2026 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/22/2026 Approved ALEJANDRO DE ARTOLA
Insulation 1/22/2026 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 1/26/2026 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 1/29/2026 Approved ALEX COLIN
Interior/Exterior Lathing 1/29/2026 Approved ALEX COLIN
ELECTRICAL-Final 4/1/2026 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/2/2026 Approved ALEJANDRO DE ARTOLA
Gas Test 4/2/2026 Approved ALEJANDRO DE ARTOLA
HVAC-Final 4/2/2026 Approved ALEJANDRO DE ARTOLA
Final 4/3/2026 OK to Issue CofO SABAS ALONSO
Footing/Foundation/Slab 4/3/2026 Approved SABAS ALONSO
Green Building Final 4/3/2026 Approved SABAS ALONSO
PLUMBING-Final 4/3/2026 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 4/3/2026 SGSOV Approved SABAS ALONSO
Service/Power Release 4/3/2026 Approved SABAS ALONSO
Smoke Detectors 4/3/2026 Approved SABAS ALONSO