7703 N WISH AVE 91406

Certificate Information: 7703 N WISH AVE 91406

Application / Permit
25010-20000-01887
Plan Check / Job No.
B25VN12088
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* New 4 car garage (first level) with 2nd story attached ADU
Permit Issued
Issued on 7/31/2025
Issuing Office
Current Status
Issued on 7/31/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/5/2025 APPLICANT
Assigned to Plan Check Engineer 5/8/2025 VARAND SARKISIAN
Corrections Issued 5/12/2025 VARAND SARKISIAN
Quality Review Completed 6/3/2025 GARO TELMI
Plan Check Approved 7/30/2025 VARAND SARKISIAN
Issued 7/31/2025 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 6/11/2025 GEVORK KARAPETYAN
Address approval Cleared 6/17/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 6/17/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/20/2025 BIAINA HARITUNIAN
Sewer availability Cleared 6/20/2025 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 7/11/2025 RUEL COLE

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Drywall Nailing 6/8/2026   

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/15/2025 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 12/23/2025 Corrections Issued GAREN HAYRAPETYAN
Footing/Foundation/Slab 1/14/2026 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 2/6/2026 Corrections Issued GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 2/11/2026 Partial Approval GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 3/9/2026 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 3/19/2026 Corrections Issued KIRK SANDERS
PLUMBING-Rough 3/19/2026 Approved KIRK SANDERS
HVAC-Rough 3/20/2026 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/2/2026 Corrections Issued KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 4/22/2026 Corrections Issued RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 4/30/2026 Approved KIRK SANDERS
Interior/Exterior Lathing 5/8/2026 Partial Approval KIRK SANDERS
Insulation 5/28/2026 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 5/28/2026 Approved MICHAEL CORTEZ
BUILDING-Rough-Frame 6/2/2026 Approved MICHAEL CORTEZ
Floor/Roof Diaphrgm/Shear Wall 6/2/2026 Approved MICHAEL CORTEZ
Green Building Rough 6/2/2026 Approved MICHAEL CORTEZ
Verify Sprinkler Sign Off 6/2/2026 Approved MICHAEL CORTEZ