19008 W HARTLAND ST 91335

Certificate Information: 19008 W HARTLAND ST 91335

Application / Permit
25010-20000-01886
Plan Check / Job No.
B25VN12078
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY (40' X 25') ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 9/12/2025
Issuing Office
Valley
Current Status
CofO in Progress on 6/25/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/30/2025 APPLICANT
Assigned to Plan Check Engineer 5/1/2025 VAHAN JIVALAGIAN
Corrections Issued 5/3/2025 VAHAN JIVALAGIAN
Quality Review Completed 5/6/2025 OMID HEDAYAT
Building Plans Picked Up 5/8/2025 APPLICANT
Plan Check Approved 9/8/2025 VAHAN JIVALAGIAN
Issued 9/12/2025 APPLICANT
CofO in Progress 6/25/2026 ARUTYUN MADATYAN

Permit Application Clearance Information

ZI Cleared 5/12/2025 ALEX VELA
Address approval Cleared 6/27/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 8/11/2025 MICHAEL BROWN
Sewer availability Cleared 8/11/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 8/14/2025 MICHAEL BROWN
Construction near power lines Cleared 8/19/2025 RIDWAN HARDY

Contact Information

Contractor Davudians Jorjik; Lic. No.: 928686-B 23345 SANDALWOOD STREET      WEST HILLS, CA 91307
Engineer Sabzehzar,, Habib; Lic. No.: C50442 8180 N PRICE AVE      FRESNO, CA 93720

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/16/2025 Partial Approval ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 11/4/2025 Approved ARUTYUN MADATYAN
Footing/Foundation/Slab 11/4/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 12/8/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 12/23/2025 Partial Approval ARUTYUN MADATYAN
BUILDING-Rough-Frame 1/7/2026 Conditional Approval ARUTYUN MADATYAN
Rough-Elec/Plmb/HVAC 1/7/2026 Approved ARUTYUN MADATYAN
Green Building Rough 1/8/2026 Approved ARUTYUN MADATYAN
Verify Sprinkler Sign Off 1/8/2026 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 1/20/2026 Approved ARUTYUN MADATYAN
Insulation 1/20/2026 Approved ARUTYUN MADATYAN
Drywall Nailing 1/26/2026 Approved ARUTYUN MADATYAN
Shower Pan 2/9/2026 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 2/11/2026 Partial Approval ARUTYUN MADATYAN
PLUMBING-Rough 3/11/2026 Partial Approval ARUTYUN MADATYAN
Sewer 3/11/2026 Approved ARUTYUN MADATYAN
Underground Mechanical 3/11/2026 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 5/22/2026 Approved ARUTYUN MADATYAN
Final 5/22/2026 Corrections Issued ARUTYUN MADATYAN
Green Building Final 5/22/2026 Approved ARUTYUN MADATYAN
HVAC-Final 5/22/2026 Approved ARUTYUN MADATYAN
PLUMBING-Final 5/22/2026 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 5/22/2026 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 5/22/2026 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 5/22/2026 Approved ARUTYUN MADATYAN
Final 6/17/2026 OK to Issue CofO ARUTYUN MADATYAN
Service/Power Release 6/17/2026 Approved ARUTYUN MADATYAN