11323-11323 1/2 N MONOGRAM AVE 91344
Certificate Information: 11323-11323 1/2 N MONOGRAM AVE 91344
- Application / Permit
- 25010-20000-01878
- Plan Check / Job No.
- B25VN12064
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 1ST FLOOR NEW ADUAND 2ND FLOOR NEW SB9 UNIT
- Permit Issued
- Issued on 10/8/2025
- Issuing Office
- Current Status
- Issued on 10/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/30/2025 | APPLICANT |
| Assigned to Zoning Architect | 5/2/2025 | MEGAN KOLP |
| Assigned to Plan Check Engineer | 5/8/2025 | ARSALAN SHABESTARI |
| Corrections Issued | 5/13/2025 | ARSALAN SHABESTARI |
| Quality Review Completed | 5/23/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 8/14/2025 | ARSALAN SHABESTARI |
| Plan Check Approved | 10/8/2025 | ARSALAN SHABESTARI |
| Issued | 10/8/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/4/2025 | MICHAEL BROWN |
| Senate Bill 9 | Cleared | 6/11/2025 | ALEX VELA |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 6/17/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 6/27/2025 | MICHAEL BROWN |
| Hydrant and Access approval | Cleared | 7/15/2025 | KURT CORRAL |
| Zoning Plan Check | Cleared | 9/19/2025 | MEGAN KOLP |
| GPI Written Notices | Cleared | 10/8/2025 | ARSALAN SHABESTARI |
| Grading Pre-Inspection | Cleared | 10/8/2025 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/24/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 10/24/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/24/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Special/Order Compliance | 10/24/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 10/29/2025 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Pre-Inspection | 12/23/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 1/8/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 1/8/2026 | Conditional Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 1/8/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2026 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 1/8/2026 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 1/30/2026 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 1/30/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 1/30/2026 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Rough | 1/30/2026 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 1/30/2026 | Approved | CHRISTOPHER ROJAS |
| Sewer | 1/30/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 1/30/2026 | Approved | CHRISTOPHER ROJAS |
| Rough-Elec/Plmb/HVAC | 2/12/2026 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 2/12/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Insulation | 2/24/2026 | Corrections Issued | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 2/24/2026 | Partial Approval | MICHAEL CORTEZ |
| Insulation | 3/6/2026 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 3/6/2026 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 3/6/2026 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 3/20/2026 | Approved | KEVIN BERBERYAN |
| Shower Pan | 3/20/2026 | Approved | KEVIN BERBERYAN |