11323-11323 1/2 N MONOGRAM AVE 91344

Certificate Information: 11323-11323 1/2 N MONOGRAM AVE 91344

Application / Permit
25010-20000-01878
Plan Check / Job No.
B25VN12064
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
1ST FLOOR NEW ADUAND 2ND FLOOR NEW SB9 UNIT
Permit Issued
Issued on 10/8/2025
Issuing Office
Current Status
Issued on 10/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/30/2025 APPLICANT
Assigned to Zoning Architect 5/2/2025 MEGAN KOLP
Assigned to Plan Check Engineer 5/8/2025 ARSALAN SHABESTARI
Corrections Issued 5/13/2025 ARSALAN SHABESTARI
Quality Review Completed 5/23/2025 PRANITA SHAH
Applicant returned to address corrections 8/14/2025 ARSALAN SHABESTARI
Plan Check Approved 10/8/2025 ARSALAN SHABESTARI
Issued 10/8/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/4/2025 MICHAEL BROWN
Senate Bill 9 Cleared 6/11/2025 ALEX VELA
Eng Process Fee Ord 176,300 Cleared 6/17/2025 MICHAEL BROWN
Sewer availability Cleared 6/17/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 6/27/2025 MICHAEL BROWN
Hydrant and Access approval Cleared 7/15/2025 KURT CORRAL
Zoning Plan Check Cleared 9/19/2025 MEGAN KOLP
GPI Written Notices Cleared 10/8/2025 ARSALAN SHABESTARI
Grading Pre-Inspection Cleared 10/8/2025 ARSALAN SHABESTARI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/24/2025 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 10/24/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 10/24/2025 Partial Approval CHRISTOPHER ROJAS
Special/Order Compliance 10/24/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 10/29/2025 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 12/8/2025 Partial Approval CHRISTOPHER ROJAS
Pre-Inspection 12/23/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/8/2026 Corrections Issued CHRISTOPHER ROJAS
Deputy Wood Construction 1/8/2026 Conditional Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 1/8/2026 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 1/8/2026 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 1/8/2026 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/30/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 1/30/2026 Approved CHRISTOPHER ROJAS
HVAC-Rough 1/30/2026 Approved CHRISTOPHER ROJAS
MERV13>=Rough 1/30/2026 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 1/30/2026 Approved CHRISTOPHER ROJAS
Sewer 1/30/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 1/30/2026 Approved CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 2/12/2026 Approved CHRISTOPHER ROJAS
Underground Mechanical 2/12/2026 Partial Approval CHRISTOPHER ROJAS
Insulation 2/24/2026 Corrections Issued MICHAEL CORTEZ
Interior/Exterior Lathing 2/24/2026 Partial Approval MICHAEL CORTEZ
Insulation 3/6/2026 Approved JAVIER RAMOS JR
Pre-Inspection 3/6/2026 Partial Approval JAVIER RAMOS JR
Shower Pan 3/6/2026 Approved JAVIER RAMOS JR
Drywall Nailing 3/20/2026 Approved KEVIN BERBERYAN
Shower Pan 3/20/2026 Approved KEVIN BERBERYAN