632 N RADCLIFFE AVE 90272

Certificate Information: 632 N RADCLIFFE AVE 90272

Application / Permit
25010-20000-01870
Plan Check / Job No.
B25VN12048
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/27/2025
Issuing Office
Valley
Current Status
Issued on 5/27/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/30/2025 APPLICANT
Assigned to Plan Check Engineer 4/30/2025 SARKIS HARABEDIAN
Corrections Issued 4/30/2025 SARKIS HARABEDIAN
Building Plans Picked Up 5/6/2025 APPLICANT
Plan Check Approved 5/27/2025 SARKIS HARABEDIAN
Issued 5/27/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/13/2025 SAFA JAVANMARDI
Public Works-Highway Ded. Cleared 5/13/2025 SARKIS HARABEDIAN
Public Works-Sewers Cleared 5/13/2025 SARKIS HARABEDIAN
Roof/Waste drainage to street Cleared 5/13/2025 SAFA JAVANMARDI
Sewer availability Cleared 5/13/2025 SAFA JAVANMARDI
Hydrant and Access approval Cleared 5/22/2025 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

PLUMBING-Final 6/8/2026   
HVAC-Final 6/8/2026   

Inspection Request History

PLUMBING-Rough 6/10/2025 Conditional Approval STEPHANIE SWANSON
Sewer 6/10/2025 Approved STEPHANIE SWANSON
Footing/Foundation/Slab 6/17/2025 Approved KENNETH NAGLE
Footing/Foundation/Slab 6/17/2025 Not Ready for Inspection STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 7/7/2025 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 7/29/2025 Partial Approval STEPHANIE SWANSON
Deputy Wood Construction 8/6/2025 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 8/6/2025 Partial Approval STEPHANIE SWANSON
HVAC-Rough 8/12/2025 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 8/19/2025 Approved BOBBY KEY
HVAC-Rough 8/19/2025 Approved BOBBY KEY
PLUMBING-Rough 8/19/2025 Approved BOBBY KEY
BUILDING-Rough-Frame 8/20/2025 Corrections Issued STEPHANIE SWANSON
Green Building Rough 8/20/2025 Not Ready for Inspection STEPHANIE SWANSON
Verify Sprinkler Sign Off 8/20/2025 Not Ready for Inspection STEPHANIE SWANSON
BUILDING-Rough-Frame 8/25/2025 Partial Approval STEPHANIE SWANSON
Green Building Rough 8/25/2025 Not Ready for Inspection STEPHANIE SWANSON
Verify Sprinkler Sign Off 8/25/2025 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 9/2/2025 Approved TEMISTOCLES CAAL
Green Building Rough 9/2/2025 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 9/2/2025 Partial Approval TEMISTOCLES CAAL
Insulation 9/17/2025 Approved STEPHANIE SWANSON
Shower Pan 9/17/2025 Approved STEPHANIE SWANSON
Drywall Nailing 10/1/2025 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 10/1/2025 Approved STEPHANIE SWANSON
Gas Test 10/7/2025 Approved STEPHANIE SWANSON
ELECTRICAL-Final 3/19/2026 Corrections Issued STEPHANIE SWANSON
HVAC-Final 3/19/2026 Corrections Issued STEPHANIE SWANSON
Smoke Detectors 3/19/2026 Approved STEPHANIE SWANSON
ELECTRICAL-Final 4/28/2026 Partial Approval STEPHANIE SWANSON
Service/Power Release 4/28/2026 Approved STEPHANIE SWANSON