19149 W CANTARA ST 91335
Certificate Information: 19149 W CANTARA ST 91335
- Application / Permit
- 25010-20000-01808
- Plan Check / Job No.
- B25VN11654
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 26'-0" X 26'-0" DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(a)(2). ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/12/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 5/3/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 5/5/2025 | APPLICANT |
| Issued | 5/12/2025 | APPLICANT |
| CofO in Progress | 4/29/2026 | JUAN ALVARADO |
| Permit Finaled | 5/12/2026 | JOHN JANSON |
| CofO Issued | 5/12/2026 | JOHN JANSON |
| Permit Finaled | 5/12/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/9/2025 | KEVIN CHUNG |
| Roof/Waste drainage to street | Cleared | 5/9/2025 | KEVIN CHUNG |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2025 | KEVIN CHUNG |
| Sewer availability | Cleared | 5/12/2025 | KEVIN CHUNG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/3/2025 | Corrections Issued | JEFFREY PARD |
| Sewer | 7/3/2025 | Corrections Issued | JEFFREY PARD |
| Footing/Foundation/Slab | 7/9/2025 | Conditional Approval | TROY SANDERS |
| PLUMBING-Rough | 7/9/2025 | Partial Approval | TROY SANDERS |
| Sewer | 7/9/2025 | Approved | TROY SANDERS |
| Special/Order Compliance | 7/9/2025 | Corrections Issued | TROY SANDERS |
| BUILDING-Rough-Frame | 8/15/2025 | Conditional Approval | JUAN ALVARADO |
| Green Building Rough | 8/15/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Verify Sprinkler Sign Off | 8/15/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Wood Frame | 8/15/2025 | Conditional Approval | JUAN ALVARADO |
| Deputy Wood Construction | 9/4/2025 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2025 | Approved | JUAN ALVARADO |
| Underground Mechanical | 9/30/2025 | Corrections Issued | JUAN ALVARADO |
| Rough-Elec/Plmb/HVAC | 10/10/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 10/20/2025 | Corrections Issued | HENRY KIM |
| Special/Order Compliance | 10/20/2025 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 10/23/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 10/23/2025 | Corrections Issued | JUAN ALVARADO |
| Gas Test | 10/27/2025 | Approved | JUAN ALVARADO |
| HVAC-Rough | 10/27/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 10/27/2025 | Not Ready for Inspection | JUAN ALVARADO |
| PLUMBING-Rough | 10/27/2025 | Approved | JUAN ALVARADO |
| Underground Mechanical | 10/27/2025 | Partial Approval | JUAN ALVARADO |
| BUILDING-Rough-Frame | 10/29/2025 | Approved | JUAN ALVARADO |
| Green Building Rough | 10/29/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 10/29/2025 | Approved | JUAN ALVARADO |
| Verify Sprinkler Sign Off | 10/29/2025 | Approved | JUAN ALVARADO |
| Insulation | 11/4/2025 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 11/25/2025 | Approved | JUAN ALVARADO |
| Shower Pan | 11/25/2025 | Approved | JUAN ALVARADO |
| Underground Mechanical | 1/8/2026 | Approved | JUAN ALVARADO |
| Final | 4/10/2026 | Corrections Issued | JUAN ALVARADO |
| Footing/Foundation/Slab | 4/10/2026 | Approved | JUAN ALVARADO |
| Green Building Final | 4/10/2026 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 4/10/2026 | SGSOV Not Ready | JUAN ALVARADO |
| Service/Power Release | 4/10/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Smoke Detectors | 4/10/2026 | Not Ready for Inspection | JUAN ALVARADO |
| ELECTRICAL-Final | 4/16/2026 | Approved | JUAN ALVARADO |
| Final | 4/16/2026 | Corrections Issued | JUAN ALVARADO |
| PLUMBING-Final | 4/16/2026 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 4/16/2026 | SGSOV Approved | JUAN ALVARADO |
| Service/Power Release | 4/16/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Smoke Detectors | 4/16/2026 | Approved | JUAN ALVARADO |
| Final | 4/28/2026 | OK to Issue CofO | JUAN ALVARADO |
| HVAC-Final | 4/28/2026 | Approved | JUAN ALVARADO |
| Service/Power Release | 4/28/2026 | Approved | JUAN ALVARADO |