236 N BOWLING GREEN WAY 90049

Certificate Information: 236 N BOWLING GREEN WAY 90049

Application / Permit
25010-20000-01782
Plan Check / Job No.
B25VN11545
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20'-5" X 42' 1-STORY ACCESSORY DWELLING UNIT. NFPA 13R FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/14/2025
Issuing Office
Current Status
Issued on 8/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/25/2025 APPLICANT
Assigned to Plan Check Engineer 5/1/2025 RAPHAEL ROSAS
Assigned to Zoning Architect 5/2/2025 AMIR NAKHLA
Corrections Issued 5/6/2025 RAPHAEL ROSAS
Quality Review Completed 5/9/2025 STEVEN KIM
Building Plans Picked Up 5/9/2025 APPLICANT
Applicant returned to address corrections 8/14/2025 RAPHAEL ROSAS
Plan Check Approved 8/14/2025 RAPHAEL ROSAS
Issued 8/14/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/10/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 5/12/2025 DARIN LAM
Sewer availability Cleared 5/12/2025 DARIN LAM
Low Impact Development (LID) Cleared 5/15/2025 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 5/16/2025 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 5/28/2025 RUEL COLE
Frnt yard landscape/Water mgmt Cleared 6/2/2025 DALIA MOKAYED
Zoning Plan Check Cleared 6/2/2025 RAPHAEL ROSAS
Construction near power lines Cleared 6/13/2025 WALTER RAMIREZ
GPI Written Notices Cleared 8/14/2025 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 8/14/2025 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/31/2025 No Access for Inspection CARLOS MATAMOROS
Underground Mechanical 1/2/2026 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 1/12/2026 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 1/14/2026 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 1/14/2026 Not Ready for Inspection EVAN COOPER
Excavation/Setback/Form/Re-Bar 1/29/2026 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/27/2026 Conditional Approval CARLOS MATAMOROS
Gas Test 4/27/2026 Approved CARLOS MATAMOROS
PLUMBING-Rough 4/27/2026 Approved CARLOS MATAMOROS
HVAC-Rough 4/28/2026 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 5/12/2026 Approved EVAN COOPER
BUILDING-Rough-Frame 5/15/2026 Partial Approval RYAN SALAZAR
Green Building Rough 5/15/2026 Not Ready for Inspection RYAN SALAZAR
Verify Sprinkler Sign Off 5/15/2026 Not Ready for Inspection RYAN SALAZAR
Wood Frame 5/15/2026 Partial Approval RYAN SALAZAR
Shower Pan 5/19/2026 Approved EVAN COOPER
Interior/Exterior Lathing 6/8/2026 Approved EVAN COOPER
Insulation 6/26/2026 Approved EVAN COOPER
Drywall Nailing 7/1/2026 Approved EVAN COOPER
Green Building Rough 7/1/2026 Approved EVAN COOPER