143 1/2 E 84TH ST 90003
Certificate Information: 143 1/2 E 84TH ST 90003
- Application / Permit
- 25010-20000-01751
- Plan Check / Job No.
- B25VN11350
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: NEW ONE STORY DETACHED ADU PER LAMC12.22A.33(c) and (d).
- Permit Issued
- Issued on 7/17/2025
- Issuing Office
- Current Status
- Issued on 7/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2025 | TSE MING HUANG |
| Corrections Issued | 5/2/2025 | TSE MING HUANG |
| Applicant returned to address corrections | 6/10/2025 | TSE MING HUANG |
| Applicant returned to address corrections | 7/15/2025 | SAMUEL GONZALEZ |
| Plan Check Approved | 7/17/2025 | TSE MING HUANG |
| Issued | 7/17/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/3/2025 | JILVER MAZARIEGOS |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2025 | JILVER MAZARIEGOS |
| Roof/Waste drainage to street | Cleared | 6/3/2025 | JILVER MAZARIEGOS |
| Sewer availability | Cleared | 6/3/2025 | JILVER MAZARIEGOS |
Contact Information
| Contractor | Garage Conversion And Adu General Construction Inc; Lic. No.: 1078818-B | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 7/25/2025 | Corrections Issued | BARRY HACHE |
| Underground Mechanical | 7/25/2025 | Corrections Issued | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 7/31/2025 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 7/31/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2025 | Approved | JOHN QUINTANILLA |
| Sewer | 8/14/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 11/19/2025 | Partial Approval | ANTHONY RAMOS |
| ELECTRICAL-Rough | 1/22/2026 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Rough | 1/22/2026 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 2/11/2026 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 2/11/2026 | Approved | JOHN QUINTANILLA |
| Wood Frame | 2/25/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 2/27/2026 | Approved | JOHN QUINTANILLA |
| Verify Sprinkler Sign Off | 2/27/2026 | Approved | JOHN QUINTANILLA |
| Insulation | 3/12/2026 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 3/25/2026 | Approved | JOHN QUINTANILLA |