15848 W KALISHER ST 91344

Certificate Information: 15848 W KALISHER ST 91344

Application / Permit
25010-20000-01741
Plan Check / Job No.
B25VN11301
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan New irregular shaped ADU with attached Porch per LAMC 12.22 A.33(b)(1). All work per engineer.
Permit Issued
Issued on 6/27/2025
Issuing Office
Current Status
CofO Issued on 7/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/20/2025 APPLICANT
Assigned to Plan Check Engineer 5/23/2025 NAREG ATARIAN
Corrections Issued 5/24/2025 NAREG ATARIAN
Applicant returned to address corrections 6/13/2025 NAREG ATARIAN
Applicant returned to address corrections 6/24/2025 NAREG ATARIAN
Plan Check Approved 6/27/2025 NAREG ATARIAN
Issued 6/27/2025 APPLICANT
CofO in Progress 5/8/2026 JENNIFER RABUCHIN
Permit Finaled 7/9/2026 RUBEN SALAS
CofO Issued 7/9/2026 RUBEN SALAS
Permit Finaled 7/9/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/30/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 6/2/2025 SAFA JAVANMARDI
Sewer availability Cleared 6/2/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 6/10/2025 SAFA JAVANMARDI
Construction near power lines Cleared 6/20/2025 ENRIQUE ACOSTA
GPI Written Notices Cleared 6/26/2025 GERMAN RODRIGUEZ MENDOZA
Grading Pre-Inspection Cleared 6/26/2025 GERMAN RODRIGUEZ MENDOZA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/17/2025 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 11/17/2025 Not Ready for Inspection JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 11/24/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 11/24/2025 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 12/8/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 1/26/2026 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 1/26/2026 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 1/26/2026 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 1/26/2026 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/29/2026 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 1/29/2026 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/29/2026 Approved KIRK SANDERS
Green Building Rough 1/29/2026 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 1/29/2026 Approved KIRK SANDERS
Verify Sprinkler Sign Off 1/29/2026 Approved KIRK SANDERS
BUILDING-Rough-Frame 2/6/2026 Approved JENNIFER RABUCHIN
Green Building Rough 2/6/2026 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 2/6/2026 Partial Approval JENNIFER RABUCHIN
Insulation 2/12/2026 Approved JENNIFER RABUCHIN
Shower Pan 2/12/2026 Approved JENNIFER RABUCHIN
Drywall Nailing 2/17/2026 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 2/17/2026 Approved JENNIFER RABUCHIN
Drywall Nailing 2/20/2026 Approved JENNIFER RABUCHIN
Gas Test 4/3/2026 Corrections Issued JENNIFER RABUCHIN
Sewer 4/3/2026 Approved JENNIFER RABUCHIN
Underground Mechanical 4/14/2026 Partial Approval MICHAEL CORTEZ
ELECTRICAL-Final 4/24/2026 Corrections Issued JENNIFER RABUCHIN
Final 4/24/2026 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 4/24/2026 Approved JENNIFER RABUCHIN
Green Building Final 4/24/2026 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/24/2026 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 4/24/2026 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 4/24/2026 Not Ready for Inspection JENNIFER RABUCHIN
Final 4/29/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 4/29/2026 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/29/2026 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 4/29/2026 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 4/29/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/5/2026 Approved JENNIFER RABUCHIN
HVAC-Final 5/5/2026 Approved JENNIFER RABUCHIN
PLUMBING-Final 5/5/2026 Approved JENNIFER RABUCHIN
Final 5/6/2026 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 5/6/2026 Approved JENNIFER RABUCHIN
Service/Power Release 5/6/2026 Approved JENNIFER RABUCHIN