8663 N RINCON AVE 91352

Certificate Information: 8663 N RINCON AVE 91352

Application / Permit
25010-20000-01687
Plan Check / Job No.
B25VN11015
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW DETACHED 2-STORY ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(b)(1) PER ENGINEERING
Permit Issued
Issued on 9/9/2025
Issuing Office
Current Status
Issued on 9/9/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/24/2025 APPLICANT
Assigned to Plan Check Engineer 5/15/2025 ALFRED RAMIREZ
Corrections Issued 5/21/2025 ALFRED RAMIREZ
Quality Review Completed 5/28/2025 STEVEN KIM
Applicant returned to address corrections 8/28/2025 ALFRED RAMIREZ
Plan Check Approved 9/3/2025 ALFRED RAMIREZ
Issued 9/9/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/28/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 6/27/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 7/1/2025 MICHAEL BROWN
Sewer availability Cleared 7/1/2025 MICHAEL BROWN
Construction near power lines Cleared 7/17/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Shagirian,, Ashot; Lic. No.: NA79415       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/24/2025 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 9/24/2025 Corrections Issued MATTHEW NELSON
Sewer 9/24/2025 Corrections Issued MATTHEW NELSON
Underground Mechanical 9/24/2025 Not Ready for Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 9/30/2025 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 9/30/2025 Corrections Issued MATTHEW NELSON
Sewer 9/30/2025 Not Ready for Inspection MATTHEW NELSON
Underground Mechanical 9/30/2025 Not Ready for Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 10/3/2025 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 10/3/2025 Partial Approval VINCENT HANLEY
Sewer 10/3/2025 Approved VINCENT HANLEY
Deputy Reinf. Concrete 10/6/2025 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 10/6/2025 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 10/28/2025 Corrections Issued MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 12/9/2025 Partial Approval MATTHEW NELSON
Wood Frame 12/9/2025 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 1/5/2026 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 1/5/2026 Corrections Issued MATTHEW NELSON
Green Building Rough 1/5/2026 Approved MATTHEW NELSON
HVAC-Rough 1/5/2026 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 1/5/2026 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 1/5/2026 Approved MATTHEW NELSON
HVAC-Rough 2/3/2026 Approved MATTHEW NELSON
Interior/Exterior Lathing 2/3/2026 Partial Approval MATTHEW NELSON
Insulation 2/9/2026 Approved MATTHEW NELSON
Drywall Nailing 2/12/2026 Approved MATTHEW NELSON