5745 N NATICK AVE 91411
Certificate Information: 5745 N NATICK AVE 91411
- Application / Permit
- 25010-20000-01674
- Plan Check / Job No.
- B25VN10924
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW FULLY ELECTRIC DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1).
- Permit Issued
- Issued on 6/6/2025
- Issuing Office
- Current Status
- CofO Issued on 10/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 4/26/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/30/2025 | APPLICANT |
| Plan Check Approved | 6/6/2025 | GIOVANNY CHAVEZ |
| Issued | 6/6/2025 | APPLICANT |
| CofO in Progress | 10/14/2025 | RYAN SALAZAR |
| CofO Issued | 10/16/2025 | RUBEN SALAS |
| Permit Finaled | 10/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/2/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 5/2/2025 | RYAN CASTRO |
| Construction near power lines | Cleared | 5/30/2025 | GEVORK KARAPETYAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 6/5/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Productive Home Renovation Inc; Lic. No.: 1076623-B | 12444 VICTORY BLVD #402 NORTH HOLLYWOOD, CA 91606 |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/10/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 7/10/2025 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Green Building Rough | 7/22/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 7/22/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Sewer | 7/22/2025 | Approved | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 7/22/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Insulation | 7/24/2025 | Partial Approval | LOUIS ESCOTO |
| Drywall Nailing | 7/30/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2025 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 7/30/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/18/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 8/18/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 8/18/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 8/18/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 8/18/2025 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 8/18/2025 | Approved | RYAN SALAZAR |
| Insulation | 8/22/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 8/22/2025 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 8/22/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 8/27/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 8/27/2025 | Approved | RYAN SALAZAR |
| Final | 10/10/2025 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 10/10/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 10/10/2025 | SGSOV Not Required | RYAN SALAZAR |
| Service/Power Release | 10/10/2025 | Approved | RYAN SALAZAR |
| Smoke Detectors | 10/10/2025 | Approved | RYAN SALAZAR |