5745 N NATICK AVE 91411

Certificate Information: 5745 N NATICK AVE 91411

Application / Permit
25010-20000-01674
Plan Check / Job No.
B25VN10924
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW FULLY ELECTRIC DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1).
Permit Issued
Issued on 6/6/2025
Issuing Office
Current Status
CofO Issued on 10/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2025 APPLICANT
Assigned to Plan Check Engineer 4/25/2025 JEROME MAGAT PALMA
Corrections Issued 4/26/2025 JEROME MAGAT PALMA
Building Plans Picked Up 4/30/2025 APPLICANT
Plan Check Approved 6/6/2025 GIOVANNY CHAVEZ
Issued 6/6/2025 APPLICANT
CofO in Progress 10/14/2025 RYAN SALAZAR
CofO Issued 10/16/2025 RUBEN SALAS
Permit Finaled 10/16/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/2/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 5/2/2025 RYAN CASTRO
Construction near power lines Cleared 5/30/2025 GEVORK KARAPETYAN
Eng Process Fee Ord 176,300 Cleared 6/5/2025 MICHAEL BROWN
Sewer availability Cleared 6/5/2025 MICHAEL BROWN

Contact Information

Contractor Productive Home Renovation Inc; Lic. No.: 1076623-B 12444 VICTORY BLVD #402      NORTH HOLLYWOOD, CA 91606
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/10/2025 Approved RYAN SALAZAR
Underground Mechanical 7/10/2025 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/22/2025 Partial Approval GAREN HAYRAPETYAN
Green Building Rough 7/22/2025 Not Ready for Inspection GAREN HAYRAPETYAN
PLUMBING-Rough 7/22/2025 Partial Approval GAREN HAYRAPETYAN
Sewer 7/22/2025 Approved GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 7/22/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Insulation 7/24/2025 Partial Approval LOUIS ESCOTO
Drywall Nailing 7/30/2025 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Partial Approval JENNIFER RABUCHIN
Green Building Rough 7/30/2025 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/18/2025 Approved RYAN SALAZAR
ELECTRICAL-Rough 8/18/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 8/18/2025 Approved RYAN SALAZAR
Green Building Rough 8/18/2025 Approved RYAN SALAZAR
HVAC-Rough 8/18/2025 Approved RYAN SALAZAR
PLUMBING-Rough 8/18/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 8/18/2025 Approved RYAN SALAZAR
Insulation 8/22/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/22/2025 Partial Approval RYAN SALAZAR
Shower Pan 8/22/2025 Approved RYAN SALAZAR
Drywall Nailing 8/27/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/27/2025 Approved RYAN SALAZAR
Final 10/10/2025 OK to Issue CofO RYAN SALAZAR
Green Building Final 10/10/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 10/10/2025 SGSOV Not Required RYAN SALAZAR
Service/Power Release 10/10/2025 Approved RYAN SALAZAR
Smoke Detectors 10/10/2025 Approved RYAN SALAZAR