8524 N DE CELIS PL 91343
Certificate Information: 8524 N DE CELIS PL 91343
- Application / Permit
- 25010-20000-01657
- Plan Check / Job No.
- B25VN10861
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW DETACHED 2ND DWELLING UNIT PER WB9 TWO-UNIT DEVELOPMENT PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
- Permit Issued
- Issued on 10/21/2025
- Issuing Office
- Current Status
- CofO in Progress on 4/24/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/18/2025 | APPLICANT |
| Assigned to Zoning Architect | 5/2/2025 | KAITA SAITO |
| Assigned to Plan Check Engineer | 5/8/2025 | ALFRED RAMIREZ |
| Corrections Issued | 5/11/2025 | ALFRED RAMIREZ |
| Quality Review Completed | 5/15/2025 | STEVEN KIM |
| Building Plans Picked Up | 5/16/2025 | APPLICANT |
| Plan Check Approved | 10/21/2025 | ALFRED RAMIREZ |
| Issued | 10/21/2025 | APPLICANT |
| CofO in Progress | 4/24/2026 | KIRK SANDERS |
Permit Application Clearance Information
| Address approval | Cleared | 5/16/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 5/16/2025 | BIAINA HARITUNIAN |
| Senate Bill 9 | Cleared | 5/19/2025 | ALEX VELA |
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/13/2025 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 8/21/2025 | FRANK GOMEZ |
| Zoning Plan Check | Cleared | 9/18/2025 | KAITA SAITO |
| Construction near power lines | Cleared | 10/14/2025 | EDGAR PASCUA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/24/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Special/Order Compliance | 11/24/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 12/2/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Sewer | 12/22/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 12/29/2025 | Conditional Approval | GAREN HAYRAPETYAN |
| HVAC-Rough | 12/29/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 12/29/2025 | Approved | GAREN HAYRAPETYAN |
| Special/Order Compliance | 12/29/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 1/6/2026 | Partial Approval | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 1/8/2026 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 1/8/2026 | Approved | GAREN HAYRAPETYAN |
| Special/Order Compliance | 1/8/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 1/8/2026 | Approved | GAREN HAYRAPETYAN |
| Insulation | 1/13/2026 | Conditional Approval | GAREN HAYRAPETYAN |
| Shower Pan | 1/13/2026 | Approved | GAREN HAYRAPETYAN |
| Underground Mechanical | 1/13/2026 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 1/21/2026 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 1/21/2026 | Approved | MICHAEL CORTEZ |
| Final | 3/19/2026 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 3/19/2026 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 3/19/2026 | SGSOV Not Ready | KIRK SANDERS |
| Service/Power Release | 3/19/2026 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 3/19/2026 | Approved | KIRK SANDERS |
| Final | 4/22/2026 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 4/22/2026 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/22/2026 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 4/22/2026 | Not Ready for Inspection | KIRK SANDERS |
| Final | 4/23/2026 | OK to Issue CofO | KIRK SANDERS |
| Service/Power Release | 4/23/2026 | Approved | KIRK SANDERS |