9603 N ETIWANDA AVE 91325
Certificate Information: 9603 N ETIWANDA AVE 91325
- Application / Permit
- 25010-20000-01641
- Plan Check / Job No.
- B25VN10703
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- TWO (N) 1-STORY SFD'S PER SB9 TWO UNIT DEVELOPMENT CREATING A DUPLEX (NFPA-13 FIRE SPRINKLERS THROUGHOUT). Address: 18301 W Halsted St & 9603 N Etiwanda Ave
- Permit Issued
- Issued on 11/25/2025
- Issuing Office
- Current Status
- Issued on 11/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/18/2025 | APPLICANT |
| Assigned to Zoning Architect | 5/2/2025 | MEGAN KOLP |
| Assigned to Plan Check Engineer | 5/8/2025 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/27/2025 | NILOOFAR MEHRAIN |
| Quality Review Completed | 5/30/2025 | JASON HEALEY |
| Applicant returned to address corrections | 7/19/2025 | NILOOFAR MEHRAIN |
| Plan Check Approved | 9/9/2025 | NILOOFAR MEHRAIN |
| Issued | 11/25/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/11/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2025 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 6/13/2025 | ERNEST TSE |
| Sewer availability | Cleared | 6/13/2025 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 6/17/2025 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 6/25/2025 | BIAINA HARITUNIAN |
| Senate Bill 9 | Cleared | 7/10/2025 | MAYELA VILLA |
| Zoning Plan Check | Cleared | 8/12/2025 | MEGAN KOLP |
Contact Information
| Architect | Stockton,, Richard Kenneth; Lic. No.: C35492 | 20140 ZIMMERMAN PLACE SANTA CLARITA, CA 91390 |
| Contractor | Owner-Builder | , |
| Engineer | Freitas,, Richard Gomes; Lic. No.: C49072 | 417 S. ASSOCIATED ROAD #131 BREA, CA 92821 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/10/2025 | Partial Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 12/19/2025 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2026 | Partial Approval | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 3/2/2026 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/3/2026 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 3/5/2026 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/11/2026 | Approved | JACK KARGODORIAN |
| Green Building Rough | 3/11/2026 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 3/11/2026 | Approved | JACK KARGODORIAN |
| Deputy Steel/Welding | 3/12/2026 | Conditional Approval | ROBERT GOLD |
| Insulation | 3/16/2026 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 3/16/2026 | Partial Approval | DAVID SCANTLIN |
| Interior/Exterior Lathing | 3/18/2026 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 3/23/2026 | Approved | DAVID SCANTLIN |
| Final | 5/28/2026 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 5/28/2026 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 5/28/2026 | SGSOV No Gas | ROBERT GOLD |
| Service/Power Release | 5/28/2026 | Not Required | ROBERT GOLD |
| Smoke Detectors | 5/28/2026 | Approved | ROBERT GOLD |
| Final | 6/1/2026 | Not Ready for Inspection | JACK KARGODORIAN |