4528 N MATILIJA AVE 91423
Certificate Information: 4528 N MATILIJA AVE 91423
- Application / Permit
- 25010-20000-01636
- Plan Check / Job No.
- B25VN10688
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW DETACHED PATIO COVER WITH ENCLOSED EXTERIOR ACCESS ONLY BATHROOM.
- Permit Issued
- Issued on 5/21/2025
- Issuing Office
- Current Status
- CofO Issued on 2/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2025 | JESSE ARELLANO |
| Corrections Issued | 4/26/2025 | JESSE ARELLANO |
| Building Plans Picked Up | 4/28/2025 | APPLICANT |
| Applicant returned to address corrections | 5/16/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 5/21/2025 | YAQUB MIRZA |
| Issued | 5/21/2025 | APPLICANT |
| CofO in Progress | 1/26/2026 | MISAEL ESPARZA |
| Permit Finaled | 2/12/2026 | RUBEN SALAS |
| CofO Issued | 2/12/2026 | RUBEN SALAS |
| Permit Finaled | 2/12/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/1/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 5/1/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2025 | BIAINA HARITUNIAN |
| ZA Case | Cleared | 5/7/2025 | DAVID URITA |
| ZI | Cleared | 5/15/2025 | DAVID URITA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/12/2025 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/25/2025 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 7/30/2025 | Partial Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/30/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 8/1/2025 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 8/1/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/5/2025 | Conditional Approval | MISAEL ESPARZA |
| Deputy Steel/Welding | 8/5/2025 | Approved | MISAEL ESPARZA |
| Green Building Rough | 8/5/2025 | Approved | MISAEL ESPARZA |
| MERV13>=Rough | 8/5/2025 | Partial Inspection | MISAEL ESPARZA |
| Shower Pan | 8/5/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 8/5/2025 | Partial Inspection | MISAEL ESPARZA |
| Drywall Nailing | 8/18/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 8/18/2025 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 8/19/2025 | Approved | JAVIER RAMOS JR |
| Shower Pan | 8/19/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/15/2026 | Approved | MISAEL ESPARZA |
| Final | 1/15/2026 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 1/15/2026 | Approved | MISAEL ESPARZA |
| MERV13>=Final | 1/15/2026 | Approved | MISAEL ESPARZA |
| MERV13>=Rough | 1/15/2026 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/15/2026 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 1/15/2026 | Not Required | MISAEL ESPARZA |
| Smoke Detectors | 1/15/2026 | Approved | MISAEL ESPARZA |
| Final | 1/22/2026 | OK to Issue CofO | MISAEL ESPARZA |