20562 W HAYNES ST 91306

Certificate Information: 20562 W HAYNES ST 91306

Application / Permit
25010-20000-01598
Plan Check / Job No.
B25VN10286
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) PER WFPP **ePlan**
Permit Issued
Issued on 7/29/2025
Issuing Office
Current Status
CofO Issued on 6/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2025 APPLICANT
Assigned to Plan Check Engineer 5/1/2025 NILOOFAR MEHRAIN
Corrections Issued 5/8/2025 NILOOFAR MEHRAIN
Quality Review Completed 5/15/2025 JASON HEALEY
Applicant returned to address corrections 6/3/2025 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/17/2025 NILOOFAR MEHRAIN
Applicant returned to address corrections 7/15/2025 NILOOFAR MEHRAIN
Plan Check Approved 7/23/2025 NILOOFAR MEHRAIN
Issued 7/29/2025 APPLICANT
CofO in Progress 5/7/2026 ALEXANDER HANDY
Permit Finaled 6/4/2026 JOHN JANSON
CofO Issued 6/4/2026 JOHN JANSON
Permit Finaled 6/4/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/20/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/20/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/20/2025 BIAINA HARITUNIAN
Sewer availability Cleared 5/20/2025 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 5/21/2025 KURT CORRAL
ZI Cleared 5/23/2025 JASON CHAN
Construction near power lines Cleared 6/20/2025 GEVORK KARAPETYAN
Construction within easement Cleared 6/20/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/20/2025 Partial Approval ALEXANDER HANDY
Sewer 8/20/2025 Approved ALEXANDER HANDY
Excavation/Setback/Form/Re-Bar 8/25/2025 Approved ALEXANDER HANDY
Footing/Foundation/Slab 8/25/2025 Approved ALEXANDER HANDY
Special/Order Compliance 9/4/2025 Corrections Issued ALEXANDER HANDY
Verify Sprinkler Sign Off 9/4/2025 Not Ready for Inspection ALEXANDER HANDY
Wood Frame 9/4/2025 Partial Approval ALEXANDER HANDY
BUILDING-Rough-Frame 1/27/2026 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 1/27/2026 Approved ALEXANDER HANDY
HVAC-Rough 1/27/2026 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Rough 1/27/2026 Corrections Issued ALEXANDER HANDY
BUILDING-Rough-Frame 1/30/2026 Partial Approval ALEXANDER HANDY
HVAC-Rough 1/30/2026 Approved ALEXANDER HANDY
Interior/Exterior Lathing 1/30/2026 Partial Approval ALEXANDER HANDY
PLUMBING-Rough 1/30/2026 Approved ALEXANDER HANDY
Verify Sprinkler Sign Off 1/30/2026 Approved ALEXANDER HANDY
Insulation 2/3/2026 Corrections Issued HENRY KIM
Shower Pan 2/3/2026 Approved HENRY KIM
Insulation 2/6/2026 Approved DAVID FASTIGGI
Drywall Nailing 2/10/2026 Approved DAVID FASTIGGI
BUILDING-Rough-Frame 4/7/2026 Approved ALEXANDER HANDY
Final 4/7/2026 Corrections Issued ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 4/7/2026 SGSOV No Gas ALEXANDER HANDY
Service/Power Release 4/7/2026 Not Ready for Inspection ALEXANDER HANDY
Smoke Detectors 4/7/2026 Approved ALEXANDER HANDY
Special/Order Compliance 4/7/2026 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Final 5/6/2026 Approved ALEXANDER HANDY
Final 5/6/2026 OK to Issue CofO ALEXANDER HANDY
HVAC-Final 5/6/2026 Approved ALEXANDER HANDY
PLUMBING-Final 5/6/2026 Approved ALEXANDER HANDY
Service/Power Release 5/6/2026 Not Required ALEXANDER HANDY