4257 N CLEAR VALLEY DR 91436

Certificate Information: 4257 N CLEAR VALLEY DR 91436

Application / Permit
25010-20000-01573
Plan Check / Job No.
B25VN10108
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 25'-5" X 37'-8" 1-STORY ACCESSORY DWELLING UNIT W/ ROOFTOP DECK PER LAMC 12.22 A.33(b)(1). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/5/2025
Issuing Office
Valley
Current Status
Issued on 9/5/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/11/2025 APPLICANT
Assigned to Plan Check Engineer 4/17/2025 RAPHAEL ROSAS
Corrections Issued 4/24/2025 RAPHAEL ROSAS
Quality Review Completed 4/29/2025 STEVEN KIM
Building Plans Picked Up 5/2/2025 APPLICANT
Applicant returned to address corrections 6/23/2025 RAPHAEL ROSAS
Applicant returned to address corrections 7/29/2025 RAPHAEL ROSAS
Plan Check Approved 9/3/2025 RAPHAEL ROSAS
Issued 9/5/2025 APPLICANT

Permit Application Clearance Information

Distance to fire station Cleared 5/15/2025 FRANK GOMEZ
Hydrant and Access approval Cleared 5/15/2025 FRANK GOMEZ
Address approval Cleared 5/16/2025 TAL SHEMEN
BHO/Hillside ordinance Cleared 5/16/2025 TAL SHEMEN
BHO/Hillside ordinance Cleared 5/16/2025 TAL SHEMEN
BHO/Hillside ordinance Cleared 5/16/2025 TAL SHEMEN
BHO/Hillside ordinance Cleared 5/16/2025 TAL SHEMEN
BHO/Hillside ordinance Cleared 5/16/2025 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 5/20/2025 TAL SHEMEN
Sewer availability Cleared 5/20/2025 TAL SHEMEN
Roof/Waste drainage to street Cleared 7/30/2025 RYAN CASTRO
GPI Written Notices Cleared 8/26/2025 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 8/26/2025 RAPHAEL ROSAS

Contact Information

Contractor Jonny Appleseed Landscaping Inc; Lic. No.: 721274-B P O BOX 7010      BEVERLY HILLS, CA 90212
Engineer Garza,, Omar Leonel; Lic. No.: S5593 5050 EAGLE ROCK BOULEVARD      LOS ANGELES, CA 90041
Engineer Hamilton,, David; Lic. No.: GE2721 1641 BORDER AVE      TORRANCE, CA 90501
Geologist Haenschke,, Eirik; Lic. No.: EG1597 9616 GIERSON AVE      CHATSWORTH, CA 91311

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/13/2026 Partial Inspection JOHN KIDWELL
Deputy Drilled-In Anchors 3/4/2026 Conditional Approval PTOLEMY HILL
Footing/Foundation/Slab 3/4/2026 Corrections Issued PTOLEMY HILL
PLUMBING-Rough 3/24/2026 Not Ready for Inspection JONATHAN FRANCHINI
Excavation/Setback/Form/Re-Bar 4/10/2026 Not Ready for Inspection JONATHAN FRANCHINI
Sewer 4/10/2026 Approved JONATHAN FRANCHINI
Excavation/Setback/Form/Re-Bar 4/16/2026 Corrections Issued JONATHAN FRANCHINI
Footing/Foundation/Slab 4/16/2026 Not Ready for Inspection JONATHAN FRANCHINI
Excavation/Setback/Form/Re-Bar 4/24/2026 Not Ready for Inspection JONATHAN FRANCHINI
Masonry Wall/Backfill 4/24/2026 Not Ready for Inspection JONATHAN FRANCHINI
PLUMBING-Rough 4/24/2026 Approved JONATHAN FRANCHINI
Sewer 4/24/2026 Approved JONATHAN FRANCHINI
Excavation/Setback/Form/Re-Bar 4/27/2026 Not Ready for Inspection JOEL ORDAZ
Excavation/Setback/Form/Re-Bar 5/1/2026 Partial Approval JONATHAN FRANCHINI
Footing/Foundation/Slab 5/1/2026 Partial Approval JONATHAN FRANCHINI
Grounding or Bonding 5/1/2026 Approved JONATHAN FRANCHINI
Rough-Elec/Plmb/HVAC 5/1/2026 Approved JONATHAN FRANCHINI
Deputy Reinf. Concrete 5/4/2026 Conditional Approval PTOLEMY HILL
Masonry Wall/Backfill 5/7/2026 Partial Approval JONATHAN FRANCHINI
ELECTRICAL-Rough 5/22/2026 Partial Approval JONATHAN FRANCHINI
Excavation/Setback/Form/Re-Bar 5/22/2026 Partial Approval JONATHAN FRANCHINI
Footing/Foundation/Slab 5/22/2026 Partial Approval JONATHAN FRANCHINI
HVAC-Rough 5/22/2026 Not Ready for Inspection JONATHAN FRANCHINI
Masonry Wall/Backfill 5/22/2026 Not Ready for Inspection JONATHAN FRANCHINI
PLUMBING-Rough 5/22/2026 Partial Approval JONATHAN FRANCHINI
Rough-Elec/Plmb/HVAC 5/22/2026 Not Ready for Inspection JONATHAN FRANCHINI
Sewer 5/22/2026 Approved JONATHAN FRANCHINI
Deputy Reinf. Concrete 5/26/2026 Conditional Approval PTOLEMY HILL
Footing/Foundation/Slab 6/23/2026 Partial Approval PTOLEMY HILL
Green Building Rough 6/23/2026 Approved PTOLEMY HILL
PLUMBING-Rough 6/23/2026 Approved PTOLEMY HILL
Reinforced Concrete Frame 6/23/2026 Partial Approval PTOLEMY HILL
Verify Sprinkler Sign Off 6/23/2026 Partial Inspection JASON WILSON
Deputy Reinf. Concrete 6/25/2026 Conditional Approval PTOLEMY HILL