4257 N CLEAR VALLEY DR 91436
Certificate Information: 4257 N CLEAR VALLEY DR 91436
- Application / Permit
- 25010-20000-01573
- Plan Check / Job No.
- B25VN10108
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 25'-5" X 37'-8" 1-STORY ACCESSORY DWELLING UNIT W/ ROOFTOP DECK PER LAMC 12.22 A.33(b)(1). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/5/2025
- Issuing Office
- Valley
- Current Status
- Issued on 9/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2025 | RAPHAEL ROSAS |
| Corrections Issued | 4/24/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 4/29/2025 | STEVEN KIM |
| Building Plans Picked Up | 5/2/2025 | APPLICANT |
| Applicant returned to address corrections | 6/23/2025 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 7/29/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 9/3/2025 | RAPHAEL ROSAS |
| Issued | 9/5/2025 | APPLICANT |
Permit Application Clearance Information
| Distance to fire station | Cleared | 5/15/2025 | FRANK GOMEZ |
| Hydrant and Access approval | Cleared | 5/15/2025 | FRANK GOMEZ |
| Address approval | Cleared | 5/16/2025 | TAL SHEMEN |
| BHO/Hillside ordinance | Cleared | 5/16/2025 | TAL SHEMEN |
| BHO/Hillside ordinance | Cleared | 5/16/2025 | TAL SHEMEN |
| BHO/Hillside ordinance | Cleared | 5/16/2025 | TAL SHEMEN |
| BHO/Hillside ordinance | Cleared | 5/16/2025 | TAL SHEMEN |
| BHO/Hillside ordinance | Cleared | 5/16/2025 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2025 | TAL SHEMEN |
| Sewer availability | Cleared | 5/20/2025 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 7/30/2025 | RYAN CASTRO |
| GPI Written Notices | Cleared | 8/26/2025 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 8/26/2025 | RAPHAEL ROSAS |
Contact Information
| Contractor | Jonny Appleseed Landscaping Inc; Lic. No.: 721274-B | P O BOX 7010 BEVERLY HILLS, CA 90212 |
| Engineer | Garza,, Omar Leonel; Lic. No.: S5593 | 5050 EAGLE ROCK BOULEVARD LOS ANGELES, CA 90041 |
| Engineer | Hamilton,, David; Lic. No.: GE2721 | 1641 BORDER AVE TORRANCE, CA 90501 |
| Geologist | Haenschke,, Eirik; Lic. No.: EG1597 | 9616 GIERSON AVE CHATSWORTH, CA 91311 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/13/2026 | Partial Inspection | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 3/4/2026 | Conditional Approval | PTOLEMY HILL |
| Footing/Foundation/Slab | 3/4/2026 | Corrections Issued | PTOLEMY HILL |
| PLUMBING-Rough | 3/24/2026 | Not Ready for Inspection | JONATHAN FRANCHINI |
| Excavation/Setback/Form/Re-Bar | 4/10/2026 | Not Ready for Inspection | JONATHAN FRANCHINI |
| Sewer | 4/10/2026 | Approved | JONATHAN FRANCHINI |
| Excavation/Setback/Form/Re-Bar | 4/16/2026 | Corrections Issued | JONATHAN FRANCHINI |
| Footing/Foundation/Slab | 4/16/2026 | Not Ready for Inspection | JONATHAN FRANCHINI |
| Excavation/Setback/Form/Re-Bar | 4/24/2026 | Not Ready for Inspection | JONATHAN FRANCHINI |
| Masonry Wall/Backfill | 4/24/2026 | Not Ready for Inspection | JONATHAN FRANCHINI |
| PLUMBING-Rough | 4/24/2026 | Approved | JONATHAN FRANCHINI |
| Sewer | 4/24/2026 | Approved | JONATHAN FRANCHINI |
| Excavation/Setback/Form/Re-Bar | 4/27/2026 | Not Ready for Inspection | JOEL ORDAZ |
| Excavation/Setback/Form/Re-Bar | 5/1/2026 | Partial Approval | JONATHAN FRANCHINI |
| Footing/Foundation/Slab | 5/1/2026 | Partial Approval | JONATHAN FRANCHINI |
| Grounding or Bonding | 5/1/2026 | Approved | JONATHAN FRANCHINI |
| Rough-Elec/Plmb/HVAC | 5/1/2026 | Approved | JONATHAN FRANCHINI |
| Deputy Reinf. Concrete | 5/4/2026 | Conditional Approval | PTOLEMY HILL |
| Masonry Wall/Backfill | 5/7/2026 | Partial Approval | JONATHAN FRANCHINI |
| ELECTRICAL-Rough | 5/22/2026 | Partial Approval | JONATHAN FRANCHINI |
| Excavation/Setback/Form/Re-Bar | 5/22/2026 | Partial Approval | JONATHAN FRANCHINI |
| Footing/Foundation/Slab | 5/22/2026 | Partial Approval | JONATHAN FRANCHINI |
| HVAC-Rough | 5/22/2026 | Not Ready for Inspection | JONATHAN FRANCHINI |
| Masonry Wall/Backfill | 5/22/2026 | Not Ready for Inspection | JONATHAN FRANCHINI |
| PLUMBING-Rough | 5/22/2026 | Partial Approval | JONATHAN FRANCHINI |
| Rough-Elec/Plmb/HVAC | 5/22/2026 | Not Ready for Inspection | JONATHAN FRANCHINI |
| Sewer | 5/22/2026 | Approved | JONATHAN FRANCHINI |
| Deputy Reinf. Concrete | 5/26/2026 | Conditional Approval | PTOLEMY HILL |
| Footing/Foundation/Slab | 6/23/2026 | Partial Approval | PTOLEMY HILL |
| Green Building Rough | 6/23/2026 | Approved | PTOLEMY HILL |
| PLUMBING-Rough | 6/23/2026 | Approved | PTOLEMY HILL |
| Reinforced Concrete Frame | 6/23/2026 | Partial Approval | PTOLEMY HILL |
| Verify Sprinkler Sign Off | 6/23/2026 | Partial Inspection | JASON WILSON |
| Deputy Reinf. Concrete | 6/25/2026 | Conditional Approval | PTOLEMY HILL |