13310 1/2 W DYER ST 91342

Certificate Information: 13310 1/2 W DYER ST 91342

Application / Permit
25010-20000-01557
Plan Check / Job No.
B25VN10019
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan NEW ALL-ELECTRIC DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1).
Permit Issued
Issued on 5/16/2025
Issuing Office
Current Status
CofO Issued on 6/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2025 APPLICANT
Assigned to Plan Check Engineer 4/16/2025 ISIS ARGUETA
Corrections Issued 4/17/2025 ISIS ARGUETA
Plan Check Approved 5/16/2025 SARKIS HARABEDIAN
Issued 5/16/2025 APPLICANT
CofO in Progress 6/11/2026 KEVIN BERBERYAN
CofO Issued 6/23/2026 RUBEN SALAS
Permit Finaled 6/23/2026 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/29/2025 MANUEL TEJADA
Address approval Cleared 4/30/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 4/30/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/1/2025 BIAINA HARITUNIAN
Sewer availability Cleared 5/1/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Nagovitsyn,, Evgeny; Lic. No.: C93527 17436 ARMINTA ST      NORTHRIDGE, CA 91325

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/2/2025 Approved KEVIN BERBERYAN
PLUMBING-Rough 7/22/2025 Approved KEVIN BERBERYAN
Wood Frame 7/22/2025 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 8/1/2025 Approved KEVIN BERBERYAN
Insulation 8/1/2025 Partial Approval KEVIN BERBERYAN
Deputy Wood Construction 9/26/2025 Conditional Approval RAUL OLAGI
Gas Test 10/2/2025 Approved KEVIN BERBERYAN
Rough-Elec/Plmb/HVAC 10/2/2025 Corrections Issued KEVIN BERBERYAN
Interior/Exterior Lathing 10/8/2025 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 10/17/2025 Approved LOUIS ESCOTO
Floor/Roof Diaphrgm/Shear Wall 10/17/2025 Approved LOUIS ESCOTO
Green Building Rough 10/17/2025 Approved LOUIS ESCOTO
Insulation 10/17/2025 Approved LOUIS ESCOTO
Shower Pan 10/17/2025 Approved LOUIS ESCOTO
Verify Sprinkler Sign Off 10/17/2025 Approved LOUIS ESCOTO
Drywall Nailing 10/24/2025 Approved CHRISTOPHER MORFIN
Sewer 11/7/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 11/12/2025 Approved KEVIN BERBERYAN
Underground Mechanical 12/10/2025 Approved KEVIN BERBERYAN
Service/Power Release 12/30/2025 Corrections Issued KEVIN BERBERYAN
Service/Power Release 1/7/2026 Corrections Issued MICHEL ABAJAN
Service/Power Release 1/23/2026 Not Ready for Inspection KEVIN BERBERYAN
ELECTRICAL-Final 4/14/2026 Approved KEVIN BERBERYAN
Final 4/14/2026 Partial Inspection KEVIN BERBERYAN
Footing/Foundation/Slab 4/14/2026 Approved KEVIN BERBERYAN
Green Building Final 4/14/2026 Approved KEVIN BERBERYAN
HVAC-Final 4/14/2026 Approved KEVIN BERBERYAN
PLUMBING-Final 4/14/2026 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 4/14/2026 SGSOV Approved KEVIN BERBERYAN
Service/Power Release 4/14/2026 Approved KEVIN BERBERYAN
Smoke Detectors 4/14/2026 Approved KEVIN BERBERYAN
Final 6/11/2026 OK to Issue CofO KEVIN BERBERYAN