12952 W HUSTON ST 91423
Certificate Information: 12952 W HUSTON ST 91423
- Application / Permit
- 25010-20000-01555
- Plan Check / Job No.
- B25VN10011
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- (N) 16'-3" X 13'-0" DETACHED RECROOM W/BATHROOM (EXTERIOR ACCESS ONLY). ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/25/2025
- Issuing Office
- Current Status
- CofO Issued on 1/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 4/22/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 4/23/2025 | APPLICANT |
| Applicant returned to address corrections | 4/24/2025 | GIOVANNY CHAVEZ |
| Issued | 4/25/2025 | APPLICANT |
| CofO in Progress | 12/23/2025 | OGANES TARAKHCHYAN |
| Permit Finaled | 1/8/2026 | RUBEN SALAS |
| CofO Issued | 1/8/2026 | RUBEN SALAS |
| Permit Finaled | 1/8/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 4/23/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/16/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 5/20/2025 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 5/20/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 6/30/2025 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Rough | 6/30/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/30/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/9/2025 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 7/9/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/9/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 7/9/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 7/10/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 7/10/2025 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 7/10/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 7/24/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/24/2025 | Approved | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 8/5/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Final | 12/17/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 12/22/2025 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Final | 12/22/2025 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/22/2025 | SGSOV Not Required | OGANES TARAKHCHYAN |
| Service/Power Release | 12/22/2025 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 12/22/2025 | Approved | OGANES TARAKHCHYAN |