805 N RADCLIFFE AVE 90272
Certificate Information: 805 N RADCLIFFE AVE 90272
- Application / Permit
- 25010-20000-01545
- Plan Check / Job No.
- B25VN09948
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ****2025 LA WILDFIRE REBUILD ELIGABLE PROJECT**** REBUILD DETACHED 2-STORY ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 8/22/2025
- Issuing Office
- Current Status
- Issued on 8/22/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2025 | OMAR GARNICA |
| Corrections Issued | 4/15/2025 | OMAR GARNICA |
| Building Plans Picked Up | 4/16/2025 | APPLICANT |
| Plan Check Approved | 8/14/2025 | OMAR GARNICA |
| Issued | 8/22/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2025 | MAHELET GEBEYHU |
| Roof/Waste drainage to street | Cleared | 4/25/2025 | MAHELET GEBEYHU |
| Sewer availability | Cleared | 4/25/2025 | MAHELET GEBEYHU |
| Watercourse | Cleared | 4/25/2025 | MAHELET GEBEYHU |
| Distance to fire station | Cleared | 5/16/2025 | JOHN CONNEALLY |
| Hydrant and Access approval | Cleared | 5/16/2025 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 8/5/2025 | ERNEST TSE |
Contact Information
| Contractor | J J P Construction Inc; Lic. No.: 960864-B | 12555 VANOWEN STREET 2ND FLOOR OFC NORTH HOLLYWOOD, CA 91605 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
| Geologist | Kruger,, Mark Otto; Lic. No.: EG2345 | 10120 NATIONAL BLVD LOS ANGELES, CA 90034 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/1/2025 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/1/2025 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 10/7/2025 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2025 | Partial Approval | STEPHANIE SWANSON |
| Sewer | 11/4/2025 | Approved | STEPHANIE SWANSON |
| Underground Mechanical | 11/7/2025 | Approved | STEPHANIE SWANSON |
| Deputy Wood Construction | 12/17/2025 | Conditional Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2025 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 5/1/2026 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 5/1/2026 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 5/5/2026 | Not Ready for Inspection | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 5/6/2026 | Not Ready for Inspection | STEPHANIE SWANSON |
| Green Building Rough | 5/6/2026 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Rough | 5/6/2026 | Not Ready for Inspection | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 5/6/2026 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 5/14/2026 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 5/14/2026 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 5/14/2026 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 5/20/2026 | No Access for Inspection | MEL KHACHATOURIAN |
| Shower Pan | 5/20/2026 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 5/22/2026 | Approved | MEL KHACHATOURIAN |
| Insulation | 6/1/2026 | Approved | MICHAEL ALLEN |
| Insulation | 6/2/2026 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/5/2026 | No Result Entered | MEL KHACHATOURIAN |