10053 N AMESTOY AVE 91325
Certificate Information: 10053 N AMESTOY AVE 91325
- Application / Permit
- 25010-20000-01544
- Plan Check / Job No.
- B25VN09942
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW 1-STORY DETACHED ADU PER LAMC 12.22 A.33(b)(1)
- Permit Issued
- Issued on 7/8/2025
- Issuing Office
- Current Status
- CofO Issued on 6/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2025 | JESSE VIDUYA |
| Corrections Issued | 5/9/2025 | JESSE VIDUYA |
| Quality Review Completed | 5/20/2025 | GARO TELMI |
| Applicant returned to address corrections | 7/2/2025 | JESSE VIDUYA |
| Plan Check Approved | 7/8/2025 | JESSE VIDUYA |
| Issued | 7/8/2025 | APPLICANT |
| CofO in Progress | 4/22/2026 | JENNIFER RABUCHIN |
| Permit Finaled | 6/8/2026 | RUBEN SALAS |
| CofO Issued | 6/8/2026 | RUBEN SALAS |
| Permit Finaled | 6/8/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/30/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/30/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 5/30/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 5/30/2025 | RYAN CASTRO |
| Construction near power lines | Cleared | 6/24/2025 | GEVORK KARAPETYAN |
| GPI Written Notices | Cleared | 7/2/2025 | JESSE VIDUYA |
| Grading Pre-Inspection | Cleared | 7/2/2025 | JESSE VIDUYA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zolfaghari,, Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/17/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Excavation/Setback/Form/Re-Bar | 7/25/2025 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 7/25/2025 | Approved | CHRISTOPHER ROJAS |
| Sewer | 7/25/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Sewer | 7/28/2025 | Approved | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 7/28/2025 | Approved | NICHOLAS TROWBRIDGE |
| Deputy Reinf. Concrete | 7/29/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 9/17/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 10/8/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 10/20/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 10/20/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 10/27/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 10/27/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 10/27/2025 | Approved | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 10/27/2025 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 11/3/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 11/18/2025 | Approved | NICHOLAS TROWBRIDGE |
| Shower Pan | 11/21/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/10/2025 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 12/10/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 3/31/2026 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 4/6/2026 | Approved | DAVID ANDERSON |
| Service/Power Release | 4/6/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Final | 4/8/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 4/8/2026 | SGSOV No Gas | KEVIN BERBERYAN |
| Smoke Detectors | 4/8/2026 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 4/10/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 4/10/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 4/10/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Final | 4/10/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 4/15/2026 | Approved | WAYNE REGESTER |
| Final | 4/15/2026 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 4/15/2026 | Approved | WAYNE REGESTER |
| HVAC-Final | 4/15/2026 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 4/15/2026 | Approved | WAYNE REGESTER |
| Service/Power Release | 4/15/2026 | Approved | WAYNE REGESTER |
| Final | 4/20/2026 | OK to Issue CofO | JENNIFER RABUCHIN |