4927 N LEDGE AVE ADU 91601

Certificate Information: 4927 N LEDGE AVE ADU 91601

Application / Permit
25010-20000-01489
Plan Check / Job No.
B25VN09526
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 14'-6" X 24' DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g); EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 6/24/2025
Issuing Office
Current Status
Issued on 6/24/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/8/2025 APPLICANT
Assigned to Plan Check Engineer 4/10/2025 SELLA BENYAMIN
Corrections Issued 4/15/2025 SELLA BENYAMIN
Quality Review Completed 4/15/2025 STEVEN KIM
Building Plans Picked Up 4/18/2025 APPLICANT
Plan Check Approved 6/17/2025 SELLA BENYAMIN
Issued 6/24/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/9/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 5/9/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/9/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/22/2025 LEE GUILBEAUX
Sewer availability Cleared 5/22/2025 LEE GUILBEAUX
Construction near power lines Cleared 5/30/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/9/2025 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 7/16/2025 Partial Inspection JOSE AVILA
PLUMBING-Rough 7/16/2025 Partial Approval JOSE AVILA
Underground Mechanical 7/16/2025 Partial Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 7/22/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 7/24/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 7/25/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 8/28/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 8/28/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 8/28/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 9/10/2025 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 9/17/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/9/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 10/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/17/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 10/20/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 10/23/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 10/27/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 11/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 11/17/2025 Conditional Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 11/21/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 11/21/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 11/21/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 11/21/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 12/1/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 12/1/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Drywall Nailing 12/16/2025 Approved LOUIS ESCOTO
Shower Pan 12/19/2025 Not Ready for Inspection JOAQUIN GREENOUGH
Shower Pan 12/26/2025 Approved CHRISTOPHER MORFIN
Interior/Exterior Lathing 1/9/2026 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 3/25/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ