18020 W SEA REEF DR 90272

Certificate Information: 18020 W SEA REEF DR 90272

Application / Permit
25010-20000-01474
Plan Check / Job No.
B25VN09436
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (1)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 7/14/2025
Issuing Office
Current Status
Issued on 7/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/7/2025 APPLICANT
Assigned to Plan Check Engineer 4/9/2025 RAPHAEL ROSAS
Corrections Issued 4/14/2025 RAPHAEL ROSAS
Quality Review Completed 4/14/2025 STEVEN KIM
Building Plans Picked Up 4/15/2025 APPLICANT
Applicant returned to address corrections 5/2/2025 RAPHAEL ROSAS
Applicant returned to address corrections 6/3/2025 RAPHAEL ROSAS
Plan Check Approved 7/11/2025 RAPHAEL ROSAS
Issued 7/14/2025 APPLICANT

Permit Application Clearance Information

Distance to fire station Cleared 4/21/2025 KURT CORRAL
Hydrant and Access approval Cleared 4/21/2025 KURT CORRAL
BHO/Hillside ordinance Cleared 4/25/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 4/25/2025 SAFA JAVANMARDI
Sewer availability Cleared 4/25/2025 SAFA JAVANMARDI
Low Impact Development (LID) Cleared 6/17/2025 MITESH PATEL
Roof/Waste drainage to street Cleared 6/17/2025 SAFA JAVANMARDI

Contact Information

Contractor F S Design & Construction Inc; Lic. No.: 727272-B 20520 OXNARD ST      WOODLAND, CA 91367
Engineer Segovia,, Felipe; Lic. No.: C41102 2622 DORSET DR      TORRANCE, CA 90503

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/28/2025 Partial Approval BOBBY KEY
Footing/Foundation/Slab 8/5/2025 Approved KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 9/8/2025 Partial Approval BOBBY KEY
Interior/Exterior Lathing 12/17/2025 Partial Approval KENNETH NAGLE
BUILDING-Rough-Frame 1/6/2026 Approved BOBBY KEY
ELECTRICAL-Rough 1/6/2026 Approved BOBBY KEY
Green Building Rough 1/6/2026 Approved BOBBY KEY
HVAC-Rough 1/6/2026 Approved BOBBY KEY
Interior/Exterior Lathing 1/6/2026 Partial Approval BOBBY KEY
PLUMBING-Rough 1/6/2026 Approved BOBBY KEY
Shower Pan 1/6/2026 Approved BOBBY KEY
Verify Sprinkler Sign Off 1/6/2026 Approved BOBBY KEY
Insulation 1/12/2026 Conditional Approval JUAN VALENZUELA
Drywall Nailing 2/12/2026 Approved JUAN VALENZUELA
Insulation 2/12/2026 Approved JUAN VALENZUELA
Interior/Exterior Lathing 2/12/2026 Approved JUAN VALENZUELA