7033 N VALJEAN AVE 91406
Certificate Information: 7033 N VALJEAN AVE 91406
- Application / Permit
- 25010-20000-01463
- Plan Check / Job No.
- B25VN09334
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- (N) ONE STORY WAREHOUSE, OFFICE AND PARKING GARAGE W/ MEZZANINE, NFPA-13 FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 7/7/2025
- Issuing Office
- Current Status
- Issued on 7/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2025 | RARES BODEA |
| Assigned to Zoning Architect | 4/24/2025 | RONALD GREENE |
| Corrections Issued | 5/2/2025 | RARES BODEA |
| Quality Review Completed | 5/2/2025 | STEVEN KIM |
| Building Plans Picked Up | 5/5/2025 | APPLICANT |
| Disabled Access Plans Picked Up | 5/5/2025 | APPLICANT |
| Green Plans Picked Up | 5/5/2025 | APPLICANT |
| Applicant returned to address corrections | 5/13/2025 | RARES BODEA |
| Plan Check Approved | 7/7/2025 | RARES BODEA |
| Issued | 7/7/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/1/2025 | WALTER RAMIREZ |
| "Q" conditions | Cleared | 5/2/2025 | JASON CHAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2025 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 5/9/2025 | MARTIN FRAGOSO |
| Sewer availability | Cleared | 5/9/2025 | BIAINA HARITUNIAN |
| Highway dedication | Cleared | 6/3/2025 | BIAINA HARITUNIAN |
| Green Code | Cleared | 6/4/2025 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 6/18/2025 | JERRY KAO |
| DAS Clearance | Cleared | 6/23/2025 | NORLITO MEDRANO |
| Roof/Waste drainage to street | Cleared | 6/23/2025 | LEE GUILBEAUX |
| Zoning Plan Check | Cleared | 6/23/2025 | Ronald Greene |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
Inspector Information
| GREGORY POMISH, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDWIN GREGORYONA, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/5/2025 | Approved | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 9/11/2025 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 9/12/2025 | Conditional Approval | GREGORY POMISH |
| Deputy Reinf. Masonry | 9/16/2025 | Conditional Approval | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 9/16/2025 | Partial Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 9/16/2025 | Partial Approval | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 9/18/2025 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 9/19/2025 | Conditional Approval | GREGORY POMISH |
| Deputy Reinf. Masonry | 9/22/2025 | Conditional Approval | GREGORY POMISH |
| Deputy Reinf. Masonry | 9/23/2025 | Conditional Approval | GREGORY POMISH |
| Masonry Wall/Backfill | 9/23/2025 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Masonry | 9/26/2025 | Conditional Approval | GREGORY POMISH |
| Masonry Wall/Backfill | 9/26/2025 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Masonry | 9/30/2025 | Conditional Approval | GREGORY POMISH |
| Masonry Wall/Backfill | 9/30/2025 | Not Ready for Inspection | GREGORY POMISH |
| Masonry Wall/Backfill | 10/1/2025 | Partial Approval | GREGORY POMISH |
| Masonry Wall/Backfill | 10/8/2025 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Masonry | 10/16/2025 | Conditional Approval | GREGORY POMISH |
| Masonry Wall/Backfill | 10/16/2025 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 12/18/2025 | Conditional Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 12/18/2025 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 12/19/2025 | Conditional Approval | JEFFREY DURAN |
| Deputy Wood Construction | 12/23/2025 | Conditional Approval | GREGORY POMISH |
| Masonry Wall/Backfill | 12/23/2025 | Partial Approval | GREGORY POMISH |
| Deputy Wood Construction | 12/30/2025 | Conditional Approval | GREGORY POMISH |
| Green Building Rough | 2/11/2026 | Not Ready for Inspection | GREGORY POMISH |
| Verify Sprinkler Sign Off | 2/11/2026 | Not Ready for Inspection | GREGORY POMISH |
| Wood Frame | 2/11/2026 | Not Ready for Inspection | GREGORY POMISH |
| Green Building Rough | 4/1/2026 | Partial Approval | GREGORY POMISH |
| Verify Sprinkler Sign Off | 4/1/2026 | Partial Inspection | GREGORY POMISH |
| Wood Frame | 4/1/2026 | Partial Approval | GREGORY POMISH |
| Insulation | 4/3/2026 | Approved | GREGORY POMISH |
| Drywall Nailing | 4/9/2026 | Partial Approval | ROBERT DAVIS |
| Green Building Rough | 4/9/2026 | Partial Inspection | ROBERT DAVIS |