17109 W TUBA ST 91325
Certificate Information: 17109 W TUBA ST 91325
- Application / Permit
- 25010-20000-01441
- Plan Check / Job No.
- B25VN09256
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan New 2-STORY DETACHED ADU PER LAMC 12.22 A.33(c) AND (d) and attached recreational room with roof deck and trellis.
- Permit Issued
- Issued on 2/16/2026
- Issuing Office
- Current Status
- Issued on 2/16/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2025 | ZENA HADDIS |
| Corrections Issued | 4/30/2025 | ZENA HADDIS |
| Quality Review Completed | 5/12/2025 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 2/2/2026 | ZENA HADDIS |
| Plan Check Approved | 2/5/2026 | ZENA HADDIS |
| Issued | 2/16/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/16/2025 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 5/16/2025 | TAL SHEMEN |
| Construction near power lines | Cleared | 5/27/2025 | GEVORK KARAPETYAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2025 | TAL SHEMEN |
| Hydrant and Access approval | Cleared | 5/27/2025 | JERRY KAO |
| Sewer availability | Cleared | 5/27/2025 | TAL SHEMEN |
| Grading Pre-Inspection | Cleared | 9/13/2025 | MANUEL TEJADA |
| Miscellaneous | Cleared | 1/14/2026 | MICHAEL BROWN |
| GPI Written Notices | Cleared | 2/5/2026 | ZENA HADDIS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/8/2026 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 4/8/2026 | Approved | CHRISTOPHER ROJAS |
| Special/Order Compliance | 4/8/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 4/14/2026 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 4/14/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Insulation | 4/15/2026 | Partial Approval | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2026 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2026 | Partial Approval | CHRISTOPHER ROJAS |