16611 W KNOLLWOOD DR 91344

Certificate Information: 16611 W KNOLLWOOD DR 91344

Application / Permit
25010-20000-01431
Plan Check / Job No.
B25VN09212
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 45'-0" X 15'-11" DETACHED NEW CONSTRUCTION ACCESSORY DWELLING UNIT PER GCS 66323(a)(2). ALL WORK PER ENG.
Permit Issued
Issued on 5/19/2025
Issuing Office
Current Status
CofO Issued on 11/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2025 APPLICANT
Assigned to Plan Check Engineer 4/11/2025 ARTIN ZARUKIAN
Corrections Issued 4/12/2025 ARTIN ZARUKIAN
Building Plans Picked Up 4/15/2025 APPLICANT
Applicant returned to address corrections 5/19/2025 LUISANGEL VALENZUELA
Issued 5/19/2025 APPLICANT
CofO in Progress 11/3/2025 CHRISTOPHER ROJAS
Permit Finaled 11/18/2025 RUBEN SALAS
CofO Issued 11/18/2025 RUBEN SALAS
Permit Finaled 11/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/30/2025 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 4/30/2025 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 4/30/2025 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 4/30/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/30/2025 CARLOS AGUILERA
Sewer availability Cleared 4/30/2025 CARLOS AGUILERA
Grading Pre-Inspection Cleared 4/30/2025 MANUEL TEJADA
Roof/Waste drainage to street Cleared 5/5/2025 CARLOS AGUILERA
GPI Written Notices Cleared 5/19/2025 ARTIN ZARUKIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Nazarians,, Harmick; Lic. No.: C91232 9825 OSO AVE      CHATSWORTH, CA 91311

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/29/2025 Partial Approval CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 6/6/2025 Corrections Issued CHRISTOPHER ROJAS
Underground Mechanical 6/6/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 6/12/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/15/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/15/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 7/15/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 7/15/2025 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/23/2025 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 7/23/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 7/23/2025 Approved CHRISTOPHER ROJAS
Special/Order Compliance 7/25/2025 Corrections Issued CHRISTOPHER ROJAS
Insulation 7/28/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/13/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 8/13/2025 Approved CHRISTOPHER ROJAS
MERV13>=Rough 8/13/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 8/13/2025 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 8/13/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 8/18/2025 Partial Approval CHRISTOPHER ROJAS
Shower Pan 8/18/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 8/26/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 8/26/2025 Approved CHRISTOPHER ROJAS
Final 10/28/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 10/28/2025 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 10/28/2025 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 10/28/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 10/28/2025 Approved CHRISTOPHER ROJAS
Final 10/31/2025 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 10/31/2025 Approved CHRISTOPHER ROJAS
Service/Power Release 10/31/2025 Approved CHRISTOPHER ROJAS