18342 W DONMETZ ST 91326
Certificate Information: 18342 W DONMETZ ST 91326
- Application / Permit
- 25010-20000-01424
- Plan Check / Job No.
- B25VN09167
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- ePlan. NEW STORAGE BUILDING (NO MEP)
- Permit Issued
- Issued on 5/29/2025
- Issuing Office
- Current Status
- CofO Issued on 3/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2025 | FERNANDO FLORES |
| Corrections Issued | 4/8/2025 | FERNANDO FLORES |
| Plan Check Approved | 5/16/2025 | FERNANDO FLORES |
| Issued | 5/29/2025 | APPLICANT |
| CofO in Progress | 2/25/2026 | DAVID SCANTLIN |
| Permit Finaled | 3/3/2026 | JOHN JANSON |
| CofO Issued | 3/3/2026 | JOHN JANSON |
| Permit Finaled | 3/3/2026 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/12/2025 | ALEXANDER HELFER |
| Roof/Waste drainage to street | Cleared | 5/15/2025 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2025 | BRYAN GODINEZ |
Contact Information
| Contractor | Tuff Shed Inc; Lic. No.: 661664-B | 1777 S HARRISON STREET SUITE 600 DENVER, CO 80210 |
| Engineer | Cahalan,, Timothy Donald; Lic. No.: C80850 | 14818 FAIRWAY CIRCLE LEAWOOD, KS 66224 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/9/2025 | Corrections Issued | DAVID SCANTLIN |
| Footing/Foundation/Slab | 10/28/2025 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2026 | Approved | KRISTEN CAUSEY |
| Green Building Rough | 1/27/2026 | Not Ready for Inspection | KRISTEN CAUSEY |
| Wood Frame | 1/27/2026 | Conditional Approval | KRISTEN CAUSEY |
| Final | 2/3/2026 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 2/3/2026 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 2/3/2026 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 2/3/2026 | Approved | DAVID SCANTLIN |
| Final | 2/23/2026 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Rough | 2/23/2026 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 2/23/2026 | Approved | DAVID SCANTLIN |
| Wood Frame | 2/23/2026 | Approved | DAVID SCANTLIN |