7038 N TYRONE AVE 91405

Certificate Information: 7038 N TYRONE AVE 91405

Application / Permit
25010-20000-01418
Plan Check / Job No.
B25VN09125
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU per LAMC
Permit Issued
Issued on 4/30/2025
Issuing Office
Current Status
CofO Issued on 3/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2025 APPLICANT
Assigned to Plan Check Engineer 4/9/2025 SHANGQIN XIE
Corrections Issued 4/12/2025 SHANGQIN XIE
Plan Check Approved 4/28/2025 SHANGQIN XIE
Issued 4/30/2025 APPLICANT
CofO in Progress 2/25/2026 VINCENT HANLEY
Permit Finaled 3/17/2026 RUBEN SALAS
CofO Issued 3/17/2026 RUBEN SALAS
Permit Finaled 3/17/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/21/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 4/21/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 4/23/2025 SAFA JAVANMARDI
Sewer availability Cleared 4/23/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Vartanian,, Albert; Lic. No.: NA39989       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/27/2025 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 6/27/2025 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/7/2025 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 8/22/2025 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 8/22/2025 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/22/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 8/22/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 8/22/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 9/4/2025 Approved RYAN SALAZAR
HVAC-Rough 9/4/2025 Approved RYAN SALAZAR
PLUMBING-Rough 9/4/2025 Approved RYAN SALAZAR
Insulation 9/16/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/16/2025 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 9/24/2025 Partial Inspection RYAN SALAZAR
Drywall Nailing 9/24/2025 Approved RYAN SALAZAR
Green Building Rough 9/24/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 9/24/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/15/2025 Approved RYAN SALAZAR
Shower Pan 10/15/2025 Approved RYAN SALAZAR
Underground Mechanical 10/21/2025 Approved RYAN SALAZAR
Underground Mechanical 12/5/2025 Partial Approval DAVID MATSON
ELECTRICAL-Final 1/21/2026 Approved RYAN SALAZAR
BUILDING-Rough-Frame 2/18/2026 Approved KIRK SANDERS
Final 2/18/2026 Corrections Issued KIRK SANDERS
Green Building Final 2/18/2026 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 2/18/2026 SGSOV Not Required KIRK SANDERS
Service/Power Release 2/18/2026 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 2/18/2026 Approved KIRK SANDERS
Final 2/23/2026 OK to Issue CofO VINCENT HANLEY
HVAC-Final 2/23/2026 Approved VINCENT HANLEY
PLUMBING-Final 2/23/2026 Approved VINCENT HANLEY
Service/Power Release 2/23/2026 Approved VINCENT HANLEY