7038 N TYRONE AVE 91405
Certificate Information: 7038 N TYRONE AVE 91405
- Application / Permit
- 25010-20000-01418
- Plan Check / Job No.
- B25VN09125
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU per LAMC
- Permit Issued
- Issued on 4/30/2025
- Issuing Office
- Current Status
- CofO Issued on 3/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2025 | SHANGQIN XIE |
| Corrections Issued | 4/12/2025 | SHANGQIN XIE |
| Plan Check Approved | 4/28/2025 | SHANGQIN XIE |
| Issued | 4/30/2025 | APPLICANT |
| CofO in Progress | 2/25/2026 | VINCENT HANLEY |
| Permit Finaled | 3/17/2026 | RUBEN SALAS |
| CofO Issued | 3/17/2026 | RUBEN SALAS |
| Permit Finaled | 3/17/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/21/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 4/21/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 4/23/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vartanian,, Albert; Lic. No.: NA39989 | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/27/2025 | Partial Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 6/27/2025 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/7/2025 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 8/22/2025 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/22/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 8/22/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/22/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/4/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 9/4/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 9/4/2025 | Approved | RYAN SALAZAR |
| Insulation | 9/16/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/16/2025 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/24/2025 | Partial Inspection | RYAN SALAZAR |
| Drywall Nailing | 9/24/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/24/2025 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 9/24/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/15/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 10/15/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 10/21/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 12/5/2025 | Partial Approval | DAVID MATSON |
| ELECTRICAL-Final | 1/21/2026 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 2/18/2026 | Approved | KIRK SANDERS |
| Final | 2/18/2026 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 2/18/2026 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Not Required | KIRK SANDERS |
| Service/Power Release | 2/18/2026 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 2/18/2026 | Approved | KIRK SANDERS |
| Final | 2/23/2026 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 2/23/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 2/23/2026 | Approved | VINCENT HANLEY |
| Service/Power Release | 2/23/2026 | Approved | VINCENT HANLEY |