9016 S MCKINLEY AVE 90002
Certificate Information: 9016 S MCKINLEY AVE 90002
- Application / Permit
- 25010-20000-01410
- Plan Check / Job No.
- B25VN09042
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) **ePlan**
- Permit Issued
- Issued on 6/10/2025
- Issuing Office
- Current Status
- CofO Issued on 11/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2025 | NILOOFAR MEHRAIN |
| Corrections Issued | 4/24/2025 | NILOOFAR MEHRAIN |
| Quality Review Completed | 4/24/2025 | JASON HEALEY |
| Applicant returned to address corrections | 5/12/2025 | NILOOFAR MEHRAIN |
| Plan Check Approved | 6/3/2025 | NILOOFAR MEHRAIN |
| Issued | 6/10/2025 | APPLICANT |
| CofO in Progress | 11/21/2025 | JOHN QUINTANILLA |
| Permit Finaled | 11/22/2025 | DEROLD HAUFF |
| CofO Issued | 11/22/2025 | DEROLD HAUFF |
| Permit Finaled | 11/22/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/28/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 4/28/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 4/30/2025 | CINDY QI |
Contact Information
| Contractor | Cr Builders Llc; Lic. No.: 1131278-B | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/24/2025 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 6/24/2025 | Corrections Issued | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 6/26/2025 | Approved | JOHN QUINTANILLA |
| Sewer | 6/26/2025 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Partial Approval | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 7/8/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2025 | Approved | JOHN QUINTANILLA |
| Verify Sprinkler Sign Off | 7/8/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 7/18/2025 | Approved | JOHN QUINTANILLA |
| Rough-Elec/Plmb/HVAC | 7/18/2025 | Corrections Issued | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 7/22/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 7/22/2025 | Approved | JOHN QUINTANILLA |
| Verify Sprinkler Sign Off | 7/22/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 7/24/2025 | Approved | DEVON JACKSON |
| Drywall Nailing | 7/31/2025 | Approved | RONNIE MEDINA |
| ELECTRICAL-Final | 11/3/2025 | Corrections Issued | BRENDAN MORELLI |
| Final | 11/3/2025 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Final | 11/3/2025 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 11/3/2025 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 11/3/2025 | SGSOV No Gas | BRENDAN MORELLI |
| Service/Power Release | 11/3/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Smoke Detectors | 11/3/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 11/7/2025 | Approved | JOHN QUINTANILLA |
| Final | 11/7/2025 | OK to Issue CofO | JOHN QUINTANILLA |
| HVAC-Final | 11/7/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Final | 11/7/2025 | Approved | JOHN QUINTANILLA |
| Service/Power Release | 11/7/2025 | Approved | JOHN QUINTANILLA |