1728 N ALEXANDRIA AVE 90027

Certificate Information: 1728 N ALEXANDRIA AVE 90027

Application / Permit
25010-20000-01408
Plan Check / Job No.
B25VN09026
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(b)(1)
Permit Issued
Issued on 5/16/2025
Issuing Office
Current Status
Issued on 5/16/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/3/2025 APPLICANT
Assigned to Plan Check Engineer 4/9/2025 HAYATO TSUCHIYA
Corrections Issued 4/9/2025 HAYATO TSUCHIYA
Building Plans Picked Up 4/10/2025 APPLICANT
Applicant returned to address corrections 5/15/2025 KAMYAR EMAMI
Plan Check Approved 5/15/2025 GURUNATH NESARAJAH
Issued 5/16/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/10/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 4/10/2025 BIAINA HARITUNIAN
Sewer availability Cleared 4/10/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/15/2025 BIAINA HARITUNIAN
Miscellaneous Cleared 4/21/2025 MATHEW QUAN
Miscellaneous Cleared 4/21/2025 MATHEW QUAN
ZI Cleared 4/21/2025 MATHEW QUAN
Construction near power lines Cleared 5/5/2025 WALTER RAMIREZ
GPI Written Notices Cleared 5/15/2025 HAYATO TSUCHIYA
Grading Pre-Inspection Cleared 5/15/2025 HAYATO TSUCHIYA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/25/2025 Not Ready for Inspection ENRIQUE MIRELES
Underground Mechanical 12/1/2025 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 1/13/2026 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 4/20/2026 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 4/20/2026 Approved ENRIQUE MIRELES
Green Building Rough 4/20/2026 Approved ENRIQUE MIRELES
HVAC-Rough 4/20/2026 Approved ENRIQUE MIRELES
PLUMBING-Rough 4/20/2026 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 4/20/2026 Approved ENRIQUE MIRELES
Wood Frame 4/20/2026 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 4/24/2026 Approved ENRIQUE MIRELES
Insulation 4/24/2026 Approved ENRIQUE MIRELES
Drywall Nailing 5/8/2026 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 5/8/2026 Approved ENRIQUE MIRELES