7858 N WILBUR AVE 91356

Certificate Information: 7858 N WILBUR AVE 91356

Application / Permit
25010-20000-01389
Plan Check / Job No.
B25VN08931
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY DETACHED ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 12/17/2025
Issuing Office
Current Status
Issued on 12/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/3/2025 APPLICANT
Assigned to Plan Check Engineer 4/17/2025 ZENA HADDIS
Corrections Issued 5/2/2025 ZENA HADDIS
Quality Review Completed 5/12/2025 CHIHARU SUZUKI
Applicant returned to address corrections 5/12/2025 ZENA HADDIS
Applicant returned to address corrections 5/13/2025 ZENA HADDIS
Plan Check Approved 12/16/2025 ZENA HADDIS
Plan Check Approved 12/17/2025 ZENA HADDIS
Issued 12/17/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/22/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 7/22/2025 BIAINA HARITUNIAN
Permit Cleared 7/22/2025 BIAINA HARITUNIAN
Sewer availability Cleared 7/22/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 7/23/2025 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 8/18/2025 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez,, Gerardo; Lic. No.: C78115 1426 E STUART AVE      WEST COVINA, CA 91791

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/23/2026 Partial Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 1/29/2026 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 2/9/2026 Corrections Issued ARUTYUN MADATYAN
BUILDING-Rough-Frame 3/11/2026 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 3/11/2026 Not Ready for Inspection ARUTYUN MADATYAN
FLOOD-Proofing Certificate 3/11/2026 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 3/11/2026 Partial Approval ARUTYUN MADATYAN
Green Building Rough 3/11/2026 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 3/11/2026 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 3/24/2026 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 3/24/2026 Approved ARUTYUN MADATYAN
HVAC-Rough 3/24/2026 Approved ARUTYUN MADATYAN
Shower Pan 3/24/2026 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 3/25/2026 Corrections Issued JUAN ALVARADO
Green Building Rough 3/25/2026 Not Ready for Inspection JUAN ALVARADO
Insulation 4/2/2026 Not Ready for Inspection JUAN ALVARADO
BUILDING-Rough-Frame 4/6/2026 Approved JUAN ALVARADO
Green Building Rough 4/6/2026 Approved JUAN ALVARADO
Insulation 4/6/2026 Approved JUAN ALVARADO
Drywall Nailing 4/10/2026 Approved ARUTYUN MADATYAN